Grand Coulee Dam and the Columbia Basin Project usa final Report: November 2000
Download 5.01 Kb. Pdf ko'rish
|
- Bu sahifa navigatsiya:
- 1. The World Commission on Dams Global Case Study Programme
- 2. Context and Scope of the Grand Coulee Dam and Columbia Basin Project Case Study 2.1 Major Features of the Columbia River Basin
- Figure 2.2.1 Columbia River Basin
- Figure 2.2.1 Columbia River Basin (con’t.) Major Northwest Dams
Acronyms and Abbreviations BC British Columbia BC Hydro British Columbia Hydroelectric BIA Bureau of Indian Affairs BPA Bonneville Power Administration CBFWCP Columbia Basin Fish and Wildlife Compensation Programme CBP Columbia Basin Project CBT Columbia Basin Trust CCT Colville Confederated Tribes CEAA Canadian Entitlement Allocation Agreement cfs cubic feet per second Corps US Army Corps of Engineers CRITFC Columbia River Inter-Tribal Fish Commission DOE Department of Energy DSI Direct Service Industry EIS Environmental Impact Statement EPA Environmental Protection Agency ESA Endangered Species Act ft feet FCRPS Federal Columbia River Power System FELCC Firm Energy Load Carrying Capability FERC Federal Energy Regulatory Commission GCD Grand Coulee Dam GCFMP Grand Coulee Fish Mitigation Programme GNP Gross National Product GVP Gross value of production ha hectares ICC Indian Claims Commission IJC International Joint Commission IRA Indian Reorganisation Act kcfs thousands of cubic feet per second km kilometre kWh kilowatt-hour LRNRA Lake Roosevelt National Recreation Area m metre MAF million acre feet MOA Memorandum of Agreement NMFS National Marine Fisheries Service NPPC Northwest Power Planning Council NPS National Park Service O&M operations and maintenance PNCA Pacific Northwest Co-ordination Agreement PUD Public Utility District Reclamation US Bureau of Reclamation ROR Run of the river SOR System Operation Review TDG Total Dissolved Gas TMT Technical Management Team UCUT Upper Columbia United Tribes US United States USACE US Army Corps of Engineers USBR US Bureau of Reclamation USFWS US Fish and Wildlife Service USGS US Geological Service WCD World Commission on Dams Grand Coulee Dam and Columbia Basin Project 1 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission 1. The World Commission on Dams Global Case Study Programme The two-year mandate of the World Commission on Dams (WCD) calls for a review of the "development effectiveness" of large dams in the world. As part of the work programme, several case studies, including projects in the developed and developing nations, were conducted to provide in-depth analysis on specific dams. The Grand Coulee Dam (GCD), located in eastern Washington State within the United States (US) was selected as one of the case studies. This project is a key component of many water resources development plans for the entire Columbia River and its tributaries. Among all the case studies being conducted for the Commission, GCD is the oldest. Completed in 1941, GCD is a multi-purpose project; its purposes include irrigation, hydropower generation, flood control, fish and wildlife enhancement, and recreation. This case study is illustrative of how large water resources projects in the US Northwest have evolved in the context of changing social values, increased public concern over environmental issues, growth in scientific knowledge, and changes in the technology and socioeconomic conditions in the region. The Grand Coulee case study was carried out in two phases. In the first phase, a California-based inter- disciplinary project team, advised by WCD staff, prepared a draft scoping report. This document was reviewed and commented on by relevant stakeholder groups. A public consultative stakeholder meeting was held on 20 May 1999 in Spokane, Washington to discuss the study objectives and proposed methodology for the case study. At that time, the project team and WCD staff solicited feedback from meeting attendees. Input from the 20 May meeting was used in determining the research plan for the second phase of the study. The second phase of the project took place from July 1999 to March 2000. During this period, additional experts joined the project team to conduct field investigations, review literature, and assist in writing and reviewing sections of the report. Altogether, a team of over a dozen professionals, representing fields including water resources planning, Native American and First Nations studies, resource and agricultural economics, history, power systems engineering, and fisheries biology contributed to the compilation of this report. Additionally, in kind contributions from the Bureau of Reclamation, Bonneville Power Administration, and the Army Corps of Engineers facilitated data collection and access to key government personnel. A group of representatives of British Columbia Hydro (BCH), the Columbia Basin Trust (CBT), and other Canadian interests also contributed to the study. This report was distributed to stakeholder groups in December 1999 and was discussed at a second consultative stakeholder meeting held on 13 January 2000 in Portland, Oregon. Minutes of both consultative meetings, lists of attendees, and written comments submitted in response to the December 1999 draft report are presented in the Annex titled “Consultative Meetings and Comments”. The draft report was then revised to incorporate, where reasonable, comments and perspectives put forward at the second stakeholder meeting. This document is the case study’s final report. Several fundamental research questions put forward by the WCD affected the structure of case study data collection and analysis. These questions, which are presented below, were addressed in each WCD case study, including GCD. 1. What were the projected versus actual benefits, costs, and impacts? (Section 3) 2. What were the unexpected benefits, costs and impacts? (Sections 3 and 4) 3. What was the distribution of costs and benefits? Who gained and who lost? (Section 5) 4. How were key project decisions made? (Section 6) 5. How did the project evolve in response to changes in policies and decision-making criteria? (Section 7) 6. What lessons can be learned from the experiences of this project? (Section 8) 7. How can the development effectiveness of the project be evaluated? (Section 9) Grand Coulee Dam and Columbia Basin Project 2 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission The overarching purpose of this case study was to learn lessons from the past, focusing on those that are particularly relevant to the planning, implementation, and operation of large dams worldwide. The Commission’s approach recognises that there is not always unanimity in interpretation of data, or in the perceptions of different interest groups. In order to understand differing perceptions of development effectiveness we need to take account of the convergent and divergent views and perspectives of different stakeholder groups affected by GCD and the associated irrigated lands known as the Columbia Basin Project (CBP). This report does not adopt a single “position” (eg, it does not pass judgement on whether or not the project should have been built or how things should have been done differently) and it does not comment on the future evolution or management of GCD and CBP. The case study used existing data sources and reports in its assessment because project resource did not permit new research to be undertaken. In this respect, data availability limited the study’s findings Grand Coulee Dam and Columbia Basin Project 3 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission 2. Context and Scope of the Grand Coulee Dam and Columbia Basin Project Case Study 2.1 Major Features of the Columbia River Basin The study area for this case is the Columbia River Basin within the US and Canada. The focus is on GCD, which is located on the mainstream Columbia River, and the land irrigated by water stored in Lake Roosevelt, the reservoir created by the dam. Following common usage, the term Columbia Basin Project (CBP) refers to the portion of the overall project that involves irrigation. 1 The Columbia River is the 4th largest river in North America, running over 1 210 miles (1 953km) from its headwaters to the ocean (see Figure 1) (USDOE et al. (Main Report), 1995:2–1). 2 The river has a total catchment of almost 260 000 square miles (67 x 10 6 hectares) (USACE, 1958) – an area larger than that of France, Belgium, and the Netherlands combined. The basin includes large portions of Oregon, Washington, Idaho, and Montana, as well as the south-eastern drainage of the Canadian Province of British Columbia (USACE, 1958). The Columbia River originates in British Columbia and is bounded by the Rocky Mountain system to the east and the Cascade Range to the West. Numerous mountainous ridges in British Columbia, northern and central Idaho, and western Montana, which capture snowmelt, are the most significant contributors to the basin’s water supply (USACE, 1958:2). From Canada, the Columbia River flows mostly southwards through Washington, then westward where the Columbia comprises the Washington– Oregon border. The river then flows through the famous Columbia River Gorge, which bisects the Cascade Range near its midpoint, and eventually reaches the Pacific Ocean. The average annual runoff of the river basin exceeds 180 million acre-feet (2.219 x 10 11 m 3 ). A key land feature of the basin is the Columbia Plateau, which contains the land served by the project’s irrigation command area. The Plateau is a semi-arid and mostly treeless area of nearly 100 000 square miles (259 000km 2 ) that extends from north-central Washington to just below the border with Oregon. Land elevations in this region range from 500ft to 4 000ft (152m to 1 220m) (USDOE et al. (Main Report), 1995:2-2; USACE, 1958) The climatic conditions of the region make the Columbia River Basin primarily a snow-fed system. Snow accumulates in the mountains from November to March, then melts and produces runoff during the spring and summer. Runoff and streamflows normally peak in early June. In late summer and fall, rivers recede. Water levels tend to be lowest during October and increase very little until April (USDOE et al. (Main Report), 1995: 2-5). 2.2 Objectives and Components of GCD and CBP The US Army Corps of Engineers (hereafer referred to as “the Corps”) and the US Bureau of Reclamation (hereafter referred to as “Reclamation”) planned GCD and CBP. The Army Corps of Engineers feasibility report for the project (hereafter referred to as the “Butler Report”), officially completed in 1932, was conducted by Major John S. Butler (USACE, 1933). Reclamation released its feasibility report (hereafter referred to as the “Reclamation Report”) in the same year (USBR, 1932). The plans outlined in these studies provided the background for the actual construction of the dam and irrigation project. A dominant theme in both these reports was that revenues from power generated at GCD should be used to subsidise irrigation. Without power revenues, the cost of the reclaiming the Columbia Plateau would be much too high for farmers. Both reports indicated that the irrigation part of the project should not be started until power development was well underway. As detailed in Section 5, the decision to build the project was heavily influenced by the objective of putting people back to work during the economic depression (the Great Depression) that began in the late 1920s. Grand Coulee Dam and Columbia Basin Project 4 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission Figure 2.2.1 Columbia River Basin Grand Coulee Dam and Columbia Basin Project 5 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission 30. DWORSHAK N F Clearwater River, USCE 31. HELLS CANYON Snake River, IP 32. OXBOW Snake River, IP 33. BROWNLEE Snake River, IP 34. BLACK CANYON Payette River, USBR 35. BOISE RIVER DIVERSION Boise River, USBR 36. ANDERSON RANCH Boise River, USBR 37. MINIDOKA Snake River, USBR 38. PALISADES Snake River, USBR 39. PELTON Deschutes River, PGE 40. ROUND BUTTE Deschutes River, PGE 41. BIG CLIFF N. Santiam River, USCE 42. DETROIT N. Santiam River, USCE 43. FOSTER S. Santiam River, USCE 44. COUGAR McKenzie River, USCE 45. GREEN PETER M. Santiam River, USCE 46. DEXTER Willamelte River, USCE 47. LOOKOUT POINT Willamelte River, USCE 46. HILLS CREEK Willamelte River, USCE 49. MERWIN Lewis River, PP&L 50. YALE Lewis River, PP&L 51. SWIFT Lewis River, PP&L 52. MA YFIELD Cowlitz River, TCL 53. MOSSYROCK Cowlitz River, TCL 54. GORGE Skagit River, SCL 55. DIABLO Skagit River, SCL 56. ROSS Skagit River, SCL 57. CULMBACK Sultan River, Snohomish Co.PUD 56. LOST CREEK Rogue River, USCE 59. LUCKY PEAK Boise River, USCE Figure 2.2.1 Columbia River Basin (con’t.) Major Northwest Dams 1. BONNEVILLE Columbia River, USCE 2. THE DALLES Columbia River, USCE 3. JOHN DAY Columbia River, USCE 4, McNARY Columbia River, USCE 5. PRIEST RAPIDS Columbia River, Grant Co. PUD 6. WANAPUM Columbia River, Grant Co. PUD 7. ROCK ISLAND Columbia River, Chelan Co. PUD 8. ROCKY REACH Columbia River, Chelan Co PUD 9. WELLS Columbia River, Douglas Co. PUD 10. CHIEF JOSEPH Columbia River, USCE 11. GRAND COULEE Columblo River, USBR 12. KEENLEYSIDE Columbia River, BC Hydro 13. REVELSTOKE Columbia River, BC Hydro 14. MICA Columbia River, BC Hydro 15. CORRA LINN Kootenoy River, WKP&L 16. DUNCAN Duncon River, BC Hydro 17. LIBBY Kootenoi River, USCE 18. BOUNDARY Pend Orellle River, SCL 19. ALBENI FALLS Pend Oreille River, USCE 20. CABINET GORGE Clork Fork River, WWP 21. NOXON RAPIDS Clark Fork River, WWP 22. KERR Flathead River, MPC 23. HUNGRY HORSE Flathead River, USBR 24. CHANDLER Yokimo River, USBR 25. ROZA Yokimo River, USBR 26. Ice HARBOR Snoke River, USCE 27 LOWER MONUMENTAL Snake River, USCE 28 LITTLE GOOSE Snake River, USCE 29. LOWER GRANITE Snake River, USCE Grand Coulee Dam and Columbia Basin Project 6 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission The Butler Report, a voluminous work that examined the entire Columbia River upstream of its confluence with the Snake River, outlined a comprehensive plan of development for this stretch of the river (USACE, 1933: 1058–64). This plan proposed the construction of six dams on the Columbia River between its confluence with the Snake River and the Canadian border. The report recommended dams at Priest Rapids, Rock Island Rapids, Rocky Reach, Chelan, Foster Creek, and Grand Coulee. At the time of the Butler Report’s release, Rock Island Dam was already being constructed by a private power company (USACE, 1933: 1059). Navigation facilities were to be built up to Rocky Reach Dam. Butler determined that power generation could be increased with upstream storage, and so he also recommended regulation of Flathead and Pend Oreille Lakes and the construction of Hungry Horse Dam in Idaho and Montana. Major Butler examined multiple methods for irrigating the basin, and his Plans 4 and 4-A proposed irrigation of the Columbia Plateau through the construction of a high dam at the Grand Coulee. Plan 4, which proposed irrigation of 1 199 430 acres (485 392ha) of land with water stored in the Grand Coulee, most closely resembled the Reclamation Report plan, and it became the model upon which the actual project was built. Plan 4-A, the plan recommended by Butler, differed in that it proposed to irrigate only 1 034 110 acres (418 489ha) from the dam, while irrigating the remainder of the irrigation lands, 140 520 acres (56 866ha), by diverting water from the Priest Rapids reservoir downstream. Butler recognised that slight modifications in the designs and locations of the proposed structures would occur while he was developing a comprehensive plan as a broad framework for how best to use the waters of the Columbia River (USACE, 1933: 1064). His plan did not recommend any flood control provisions for this stretch of the Columbia River (USACE, 1933: 1061). In laying out his plan, Butler recommended that water for the purpose of irrigation be given a higher priority than water for power, and “that no power rights be granted which will interfere with future irrigation requirements” (USACE, 1933: 1066). Butler also recommended that “it be required that storage above power dams be so regulated as to interfere as little as possible with navigation and fish life above and below the dam” (USACE, 1933: 1067). The Reclamation Report was much more limited in scope than the Butler Report, focusing entirely on GCD and CBP. It presented plans for constructing the dam and irrigation works. The report concluded that firm power generated at the dam could be could be absorbed within 15 years of the dam’s completion, and that the financial feasibility of the project depended on the time needed to absorb the power (USBR, 1932: 81). Significantly, the Reclamation Report concluded that surplus from power revenues would be “sufficient to repay within forty years about 50 per cent of the cost of the irrigation development for the entire acreage of 1,200,000 acres…” (USBR, 1932: 81–82). The report also concluded that “the slower the irrigation development proceeds the smaller the amount of additional funds that will have to be advanced from the Treasury of the United States”. Finally, the report urged that “no construction on the irrigation development should be undertaken until power revenues are assured and a suitable contract for repayment of the investment in irrigation works within 40 years has been executed . . .” Although GCD was initiated under special executive authorities granted to President Roosevelt in 1933, it was eventually authorised by Congress in 1935 legislation that included the following language: That for the purpose of controlling floods, improving navigation, regulating the flow of streams of the United States, providing for storage and for the delivery of the stored waters thereof, for the reclamation of public lands and Indian reservations, and for other beneficial uses, and for the generation of electric energy as a means of financially aiding and assisting such undertakings the projects known as . . . and “Grand Coulee Dam” on the Columbia River, are hereby authorised and adopted . . . (US Congress, 1935: Section 2) The objectives outlined in this law provide the legal foundation for GCD and CBP. The language of the law shows that power generation was viewed as a means of financing other project purposes. Grand Coulee Dam and Columbia Basin Project 7 This is a working paper prepared for the World Commission on Dams as part of its information gathering activities. The views, conclusions, and recommendations contained in the working paper are not to be taken to represent the views of the Commission Download 5.01 Kb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling