Project Management in the Oil and Gas Industry
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
3.5.6 Example
The following example will illustrate the relationships between activities and how can you create them through the precedence diagram. The example in the following table shows the activities for a cast con- crete foundation under machine package and connects the machine with piping to the facilities, which is a simple example of knowing how to arrange activities, account for the overall time of the project, and identify the critical path. Pitfalls in Time Schedule Planning 99 In the above table, the first column contains the item number or the code for that item according to the project and its activities and the sub activities. Also, the main activity code may be 100 and the sub activity may be 110 and so on, but the above example is a simple case. The second column is the name of the activity, which describes the activity, and the third column is the time period for each activity in days. The fourth column specifies the relationships between activities. As for activity No. 200, which is the excavation, it is constrained by activity No. 1. Activity No. 6, which is setting the wooden form, is related to two activities, No. 300 and 500, meaning that the setting of the wooden form depends on finishing the preparation of the wooden form (item No. 300) and pouring the plain concrete (item No. 500). Figure 3.7 shows the precedence diagram and in each diagram there is a number with its time duration. Figure 3.8 shows the early start and finish for each activity by using the following equation: EF = ES + D, where EF is early finish, ES is early start, and D is duration. Start with activity number 100. The early finish (EF) of this activity is three days. Transfer this value to activities 200 and 400 in the early start (ES) rectangle zone. Item number 800 depends on 600 and 700, so it will take the higher value in the early finish (EF), which is 23 days. Put this number as the early start (ES) for activity 800. For the last activity, which has an early finish at 25 days, transfer this value to the latest finish (LF) rectangular zone. Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling