Project Management in the Oil and Gas Industry
Table 3.3 Float time calculation. No. Activity
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
- Bu sahifa navigatsiya:
- 3.5.7 Application of the PERT Method
Table 3.3 Float time calculation.
No. Activity D Earliest Latest Float Critical ES EF LS LF TF FF 100 Mobilization 3 0 3 0 3 0 0 * 200 Excavation 8 3 11 3 11 0 0 * 300 Pouring concrete foundation and piping support 10 11 21 11 21 0 0 * 400 Install piping 4 3 7 14 18 11 0 500 Install the mechanical package 1 21 22 21 22 0 0 * 600 Put the grouting 1 22 23 22 23 0 0 * 700 Connect the piping 5 7 12 18 23 11 11 800 Commissioning and start up 2 23 25 23 25 0 0 * 102 Project Management in the Oil and Gas Industry 3.5.7 Application of the PERT Method We previously reported that the implementation of the activity takes time and needs resources. The PERT team may face a problem of how to esti- mate the time of each activity, as they see that reliance on a single esti- mate time is a weak assumption and is incompatible with the conditions of uncertainty, even under the best circumstances. The external environ- mental factors surrounding the project may cause a deviation in the times of the activities planned. Accordingly, the PERT method has been found to overcome the time uncertainty. By estimating the time of each activity with three estimated time values they will be gathered together with knowing the activity esti- mate and time probability distribution curve to reach a statistical prob- ability to estimate the time of the project’s completion. This method will apply as follows. Optimistic time estimates the minimum possible time in which to do the activity, considering that all the factors affecting this activity are going smoothly. This time is usually low because all the circumstances must be good at the same time. Pessimistic time estimates the maximum possible time in which to implement the activity. It considers the worst cases that happen to delay this activity. This usually provides a higher time period with low probability. The “most likely time” presents the time period in which to perform this activity under normal conditions for all the factors affecting this activity. This value has the most probability of occurring. The PERT method correlates the relation between the above three times by using a beta distribution as in Figure 3.10. The optimistic and pessimis- tic value precincts the limits of the distribution, but the most likely value present is the frequencies of the event occurring. To define the activity time period, the activity mean time needs to be cal- culated, and this is done using the below equation. The summation of all the time periods on the critical path presents the mean time period for the project. 3.5.7.1 Statistics Calculation for Activity Time From the beta distribution, the expected or average time for each activity is calculated according to the following equation: Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling