Project Management in the Oil and Gas Industry
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
Table 4.1 Cost estimate procedure.
What The function of the estimate is to forecast a cost for a specified scope of work to allow an accurate budget to be assembled for the business. Cost estimating in its definition is uncertain and the different classes of estimates give improved levels of accuracy as more project scope detail is defined. A work breakdown structure (WBS) should be built from which estimates, schedules, and cost control can be derived. Formal documents are produced for all levels of estimate. Appraise: Order of Magnitude (OOM) accuracy range of +/ 50% Select: Class 3 accuracy range of +/ 30% Define: Class 2 accuracy range of +/ 15–20% Class 1 is +/ 10% (rarely used). Why This is done to indicate to the business the predicted cost of the project, so that the project is financially viable and can be established. How The project leader and the asset development engineer develop a WBS from the SOR. This is then discussed with the project team to allow the relevant discipline engineers to have input in the estimate. An OOM estimate will normally be factored with estimates based on the known high-level scope and equipment definition. Class 3 esti- mates will be factored based on a developed scope and equipment definition, including indirect costs. Class 2 estimates will be built up from the developed scope of the project and will be fit for purpose to give the accuracy range. When All projects must have a Class 2 at the end of Define for business sanc- tion. An estimate will be produced at the end of each development stage. The accuracy of the estimate will reflect that particular stage. Who The project leader is responsible and is supported by the estima- tor, discipline engineers, SPA, construction engineers, and the commissioning engineer. 120 Project Management in the Oil and Gas Industry side, the contractor will calculate the cost of construction in order to enter the tender and for this the contractor performs his calculation to qualify him to win the bidding. The third way is the control cost esti- mate, which is used by the owner to control costs, which will be dis- cussed later. The initial cost estimate is made after the preliminary studies of the proj- ect with an initial identification of industrial facilities, such as the number of pumps, air pumps, and compressors and the size of pipes and lines in diameter, and so on. The cost is determined at this stage on the basis of previous experience of similar projects. For example, calculating the cost is as follows: The calculation of the concrete price is calculated after determining the type of concrete. The cost of reinforced concrete can be calculated by obtaining the following information: • Quantity of steel per concrete cubic meter and the price of steel per ton • Quantity of cement in concrete mix and the price of cement ton Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling