Activity identifier - A unique alphanumeric value by which an individual activity can be distinguished. An activity identifier is assigned to each activity.

Activity label - A short descriptor for an activity. Activity labels may be placed below arrows representing activities in activity-on-arrow (AOA) diagrams.

Activity list - This documents all the activities necessary to complete a project. Each activity is accompanied by its activity identifier and a description of the work it entails.

Activity-On-Arrow (AOA) - In this network diagram, arrows represent activities and nodes represent events or milestones. AOA diagrams can only indicate finish-to-start relationships.

Activity-On-Node (AON) - In a network diagram of this nature, nodes represent activities and arrows illustrate logical relationships between activities. AON diagrams can illustrate four relationship types: start-to-start, start-to-finish, finish-to-start, and finish-to-finish.