N - Project Management Terms
Near-critical activity - A near-critical activity has only a small amount of total float, or slack time. Near-critical activities have a high chance of becoming critical since their float is easily exhausted.
Near-critical path - A series of activities with only small amounts of total float, called near-critical activities. A near-critical path may become a critical path if its float is exhausted.
Negative variance - The amount by which actual project performance is worse than planned project performance. Negative variances in time and budget show the project is taking longer and is more expensive than planned, respectively.
Negotiation - A discussion to resolve an issue between parties. Negotiations can take place at any point during an activity and may be formal or informal.