Elaine Walker, Mayor of Lovettsville Jennifer Bergel, Catoctin District School Board Representative Sally Kurtz, Catoctin District Supervisor Paul Brown, Loudoun County Office of Capital Construction
Proximate Location to Student Population Proximate Location to Student Population Co-Location of Middle & High Schools for Transportation Efficiencies Physical Characteristics (topography, floodplain, wetlands, geologic features, tree cover) Environmental & Cultural Resource Conditions (archaeological & historic inventory, rare and endangered species, Phase I Environmental)
Access & Transportation Improvements Utility Availability General Plan Policies/Zoning Surrounding Land Uses Site Availability (cost, funding, willing seller, condemnation)
Land Anticipated Funded Opening ES-25 FY-08 (Nov. 07) Fall, 2016 MS-10 FY-07 (Nov. 06) Fall, 2017 HS-10 FY-08 (Nov. 07) Fall, 2018
Facility Projected Capacity Acreage* Facility Projected Capacity Acreage* Opening ES-25 2016 875 20 ac. MS-10 2017 1350 35 ac. HS-10 2018 1800 75 ac. Acreage may increase or decrease depending on utility availability and site characteristics.
Respondents Respondents Danner Property Cangiano Property Virts Property
SCHOOL BOARD-REVIEW AND DIRECTION 10/28/08, 11/11/08,1/13/09, & 2/24/09 SCHOOL BOARD-REVIEW AND DIRECTION 10/28/08, 11/11/08,1/13/09, & 2/24/09 BOARD OF SUPERVISORS-REVIEW AND DIRECTION 11/18/08, 1/21/09 & 2/17/09 CONTRACT EXECUTED 2/24/09
Cangiano Property: 160 acres Cangiano Property: 160 acres Burgess Property: 10 acres Zoning: AR-1 Use: Schools Permitted by Special Exception; Commission Permit Required
PURCHASE PRICE PURCHASE PRICE - CANGIANO $9,925,000.00 (160.27 ac.)
- BURGESS $1,475,000.00 (10 ac.)
STUDY PERIOD TO 6/1/09 EXTENSION OF STUDY PERIOD PROVISION TO 7/1/09 CLOSING BY 7/8/09 CLOSING CONTINGENT ON SITE SUITABILITY
STUDY PERIOD IN PROGRESS - HYDROGEOLOGICAL STUDY
- DRAINFIELD STUDY
- PRELIMINARY TRANSPORTATION STUDY
- PRELIMINARY SITE LAYOUT
- THE SITE WILL BE PURCHASED IF IT IS SUITABLE FOR PUBLIC SCHOOL NEEDS. LEGISLATIVE APPLICATIONS WILL BE FILED SUBSEQUENT TO DETERMINATION.
APPLICATION PREPARATION - REQUIRED STUDIES : (3-9 MONTHS)
- TREE INVENTORY
- PHASE I ARCHAEOLOGICAL
- RARE & ENDANGERED SPECIES
- TRAFFIC STUDY
- HYDROGEOLOGICAL STUDY
- SOILS/DRAINFIELD STUDY
APPLICATION SUBMISSION 1-2 MONTHS AFTER STUDY COMPLETION
APPLICATION REVIEW APPLICATION REVIEW - CHECKLIST/ACCEPTANCE
- STAFF/REFERRAL AGENCY REVIEW
- PLANNING COMMISSION PUBLIC HEARING & RECOMMENDATION
- BOARD OF SUPERVISORS PUBLIC HEARING & ACTION
ESTIMATED TIMELINE: 8-10 MONTHS AFTER ACCEPTANCE