Exercise The following project is planned to finish at 18 weeks. Based upon information below as per week 13, how much will the project cost and time at completion? Comment on the current progress of project. Task


Download 36.07 Kb.
Sana17.06.2023
Hajmi36.07 Kb.
#1529599
Bog'liq
Practice - Project Monitoring


Exercise 1.
The following project is planned to finish at 18 weeks. Based upon information below as per week 13, how much will the project cost and time at completion? Comment on the current progress of project.


Task

BAC

WS%

WP%

AV

EV = BAC*WP%

BCWS(PV) =BAC*WS%

A

31,900

100

100

30,550

31900*100% =31900

31900*100%= 31900

B

138,000

100

100

115,000

138000*100% = 138 00

138000*100% = 138 00

C

36,000

50

30

6,000

36000*30% = 10 800

36000*50% = 18 000

D

20,300

10

40

2000

20300*40%=8120

20300*10%=2030

E

21,270

100

100

20,600

21270*100% =21270

21270*100% =21270

F

100,800

50

70

75,000

100800*70%=70560

100800*50%=50400

G

4,200

0

0

0

0

0

H

6,600

0

0

0

0

0

TOTAL

359 070 $







30550 +115000+6000+
2000+20600+
75000=
AV = 249 150$

=31900+138000+10800
+8120+21270+70560=
EV = 280 650 $

=31900+138000+18000+
+2030+21270+50400 =
PV=261 600$



Solution:
Planned duration= 18 weeks
Actual time= 13 week
BCWP (EV) = BAC*WP%
BCWS(PV) =BAC *WS%

Cost variance = EV-AV = 280 650 -249 150 = 31500$ >0


Schedule variance = EV-PV = 280650-261600=19050$>0

Cost index = EV/AV = 280650/249150 = 1.14


Schedule index =EV/PV = 280650/261600= 1.07


In order to define Cost estimation at completion (CEAC), we can have the following options:


CEAC (original) = BAC -CV = 359 070 -31500 = 327 570 $




CEAC(revised) = BAC/CI = 359070/1.14 = 314 974 $


TEAC(revised) = Planned duration (PD)/ SI($) = 18/1.07 = 16.82 weeks

As a summary, project is ahead in schedule and project budget is expected to be lower than planned budget. So that, we have savings in the cost and time. The project is in a good progress



Exercise 2.
A project, with expected total duration of 4 months, has been developing according to the Earned Value chart below:


July

Aug

Sep

Oct






BCWS

192000

192000

192000

60000

ACWP

192000

216500

170000


BCWP

173000

190000

185000

What is the project performance at the current time (September)? Please also forecast both cost CEAC and the actual completion date TEAC.

Solution:





BCWS= PV

ACWP=AV

BCWP=EV

CV($)

CI

SV(t)

SI(t)

July

192000

192000

173000













August

192000

216500

190000













September

192000

170000

185000













October

60000



















Total__BAC=636000__578500'>Total





















Current progress of the project can be defined through cost variance, schedule variance, cost index and schedule index. In order to calculate the CV, SV, CI, SI we have to find cumulative values of Earned, Planned and Actual values for each month and until month 4.


BAC= Sum of all Planned Values
CV = EV-AV CI =EV/AV
SV=EV-PV SI($) = EV/PV
Below in the table, we defined the CV, SV, CI and SI($)


BCWS= PV

ACWP=AV

BCWP=EV

CV($)

CI

SV($)

SI($)









July

192000

192000

173000

-19000

0.90

-19000

0.90

August

192000

216500

190000

-26500

0.88

-2000

0.99

September

192000

170000

185000

15000

1.09

-7000

0.96

October

60000



0

#DIV/0!

-60000

0.00

Total

BAC=636000

578500

548000

-30500

0.95

-88000

0.86

Now, we can compute the CEAC by applying the following options:


  1. CEAC(original) = BAC -CV = 636 000 –(-30500) = 666 500

  2. CEAC(revised) = BAC/CI = 636 000 /0.95 = 669 474 $

  3. CEAC(critical = pessimistic) = =

To calculate TEAC, we can do two methods: one is by EV approach, another one is Earned Schedule approach.



TEAC(revised by EV) =

TEAC(original by ES) = Actual time – SV(t) = 3 –(-0.146) = 3.146 months



TEAC(revised by ES) =

SO far we do not know what is SV(t) and SI(t), to calculate them, we need to create another table with cumulative values of EV, PV and AV for each month. Table below gives us the overall cumulative values for EV, PV and AV.



Cumulative PV (July) = PV(0) + PV(July)= 0+192000
Cumulative PV (August) = PV(0) + PV(July) +PV(August)= 0+192000 +192 000= 384000
Cumulative PV (September) = PV(0) + PV(July) +PV(August) + PV(September) = 0+192000 +192 000 +192000= 576000
Cumulative EV (July) = EV(0) + EV(July)= 0+173000
Cumulative EV (August) = EV(0) + EV(July) +EV(August)= 0+173000 +190 000= 363000
Cumulative EV (September) = EV(0) + EV(July) +EV(August) + EV(September) = 0+173000 +190 000+185000= 548000


Actual time

Months

BCWS= PV

ACWP=AV

BCWP=EV

ES

SV(t)=ES-AT

SI(t)=ES/AT

0


0

0

0




1

July

192000

192000

173000

0.901

-0.099

0.901

2

August

384000

408500

363000

1.891

-0.109

0.945

3

September

576000

578500

548000

2.854

-0.146

0.951

4

October

636000







Total

636000

578500

548000






= > ES(SEPTEMBER) =

Where c is the time increment that EV overcomes the planned value. In this case, c= 2


EV = 548000, PV(C) = 384 000, PV(c+1) = 576000


SV(t) = Earned Schedule(ES) – Actual Time(AT)
SI(t) = ES/AT

Exercise 3.
Based on following project data obtained at the end of the fifth month into the project execution, you are requested to determine actual performance and compute suitable project cost and duration estimates at completion.




Task name

Predecessor

Duration [months]

BAC [k$]

ACWP [k$]

WP
[%]

A

Design




2

100

100

100

B

Building erection

A

4

200

100

85

C

Installation of services

B

2

300

0

0

D

Production equipment installation

A

6

600

232

35



Solution:

Total project duration = 8 months Actual time = 5 months






Task name

Predecessor

Duration [months]

BAC [k$]

ACWP [k$]

WP

BCWP

WS%

BCWS

[%]

EV [k$]

% are based on the gant chart 

PV[k$]

A

Design


2

100

100

100%

100

100%

100

B

Building erection

A

4

200

100

85%

170

75%

150

C

Installation of services

B

2

300

0

0%

0

0%

0

D

Production equipment installation

A

6

600

232

35%

210

50%

300

TOTAL


1200

432


480


550

CV = EV-AV= 480-432 = 48 k$ under budget even savings


SV = EV-PV=480-550= -70k$ behind the schedule (delay)


CEAC(revised) = BAC/CI = (BAC*AV)/EV = 1080 k$
TEAC(revised) = PD/SI($) = (PD*PV)/EV = 9.17 months
Download 36.07 Kb.

Do'stlaringiz bilan baham:




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling