Exercise The following project is planned to finish at 18 weeks. Based upon information below as per week 13, how much will the project cost and time at completion? Comment on the current progress of project. Task
Download 36.07 Kb.
|
Practice - Project Monitoring
- Bu sahifa navigatsiya:
- TOTAL 359 070 $
- EV = 280 650 $ =31900+138000+18000+ +2030+21270+50400 = PV=261 600$
- BCWS= PV ACWP=AV BCWP=EV
- Total BAC=636000 578500
- CEAC(critical = pessimistic) = =
- Actual time Months BCWS= PV
- SV(t)=ES-AT SI(t)=ES/AT
- Total 636000 578500
- SV(t) = Earned Schedule(ES) – Actual Time(AT) SI(t) = ES/AT Exercise 3.
- Task name Predecessor
- % are based on the gant chart PV[k$]
- TOTAL 1200 432
- CEAC(revised) = BAC/CI = (BAC*AV)/EV = 1080 k$ TEAC(revised) = PD/SI($) = (PD*PV)/EV = 9.17 months
Exercise 1. The following project is planned to finish at 18 weeks. Based upon information below as per week 13, how much will the project cost and time at completion? Comment on the current progress of project.
Solution: Planned duration= 18 weeks Actual time= 13 week BCWP (EV) = BAC*WP% BCWS(PV) =BAC *WS% Cost variance = EV-AV = 280 650 -249 150 = 31500$ >0 Schedule variance = EV-PV = 280650-261600=19050$>0 Cost index = EV/AV = 280650/249150 = 1.14 Schedule index =EV/PV = 280650/261600= 1.07 In order to define Cost estimation at completion (CEAC), we can have the following options: CEAC (original) = BAC -CV = 359 070 -31500 = 327 570 $ CEAC(revised) = BAC/CI = 359070/1.14 = 314 974 $ TEAC(revised) = Planned duration (PD)/ SI($) = 18/1.07 = 16.82 weeks As a summary, project is ahead in schedule and project budget is expected to be lower than planned budget. So that, we have savings in the cost and time. The project is in a good progress Exercise 2. A project, with expected total duration of 4 months, has been developing according to the Earned Value chart below:
What is the project performance at the current time (September)? Please also forecast both cost CEAC and the actual completion date TEAC. Solution:
Current progress of the project can be defined through cost variance, schedule variance, cost index and schedule index. In order to calculate the CV, SV, CI, SI we have to find cumulative values of Earned, Planned and Actual values for each month and until month 4. BAC= Sum of all Planned Values CV = EV-AV CI =EV/AV SV=EV-PV SI($) = EV/PV Below in the table, we defined the CV, SV, CI and SI($)
Now, we can compute the CEAC by applying the following options: CEAC(original) = BAC -CV = 636 000 –(-30500) = 666 500 CEAC(revised) = BAC/CI = 636 000 /0.95 = 669 474 $ CEAC(critical = pessimistic) = = To calculate TEAC, we can do two methods: one is by EV approach, another one is Earned Schedule approach. TEAC(revised by EV) = TEAC(original by ES) = Actual time – SV(t) = 3 –(-0.146) = 3.146 months TEAC(revised by ES) = SO far we do not know what is SV(t) and SI(t), to calculate them, we need to create another table with cumulative values of EV, PV and AV for each month. Table below gives us the overall cumulative values for EV, PV and AV. Cumulative PV (July) = PV(0) + PV(July)= 0+192000 Cumulative PV (August) = PV(0) + PV(July) +PV(August)= 0+192000 +192 000= 384000 Cumulative PV (September) = PV(0) + PV(July) +PV(August) + PV(September) = 0+192000 +192 000 +192000= 576000 Cumulative EV (July) = EV(0) + EV(July)= 0+173000 Cumulative EV (August) = EV(0) + EV(July) +EV(August)= 0+173000 +190 000= 363000 Cumulative EV (September) = EV(0) + EV(July) +EV(August) + EV(September) = 0+173000 +190 000+185000= 548000
= > ES(SEPTEMBER) = Where c is the time increment that EV overcomes the planned value. In this case, c= 2 EV = 548000, PV(C) = 384 000, PV(c+1) = 576000 SV(t) = Earned Schedule(ES) – Actual Time(AT) SI(t) = ES/AT Exercise 3. Based on following project data obtained at the end of the fifth month into the project execution, you are requested to determine actual performance and compute suitable project cost and duration estimates at completion.
Solution: Total project duration = 8 months Actual time = 5 months
CV = EV-AV= 480-432 = 48 k$ under budget even savings SV = EV-PV=480-550= -70k$ behind the schedule (delay) CEAC(revised) = BAC/CI = (BAC*AV)/EV = 1080 k$ TEAC(revised) = PD/SI($) = (PD*PV)/EV = 9.17 months Download 36.07 Kb. Do'stlaringiz bilan baham: |
ma'muriyatiga murojaat qiling