ts –to‘liq sikl vaqti
ts=t3+tn+tob.k+tper=0,004+0,003+0,003+0,005=0,015
t3 gruntni kesish uchun ketgan vaqt, soat
=16.27/1000*4,8=0,003 soat
- 16.27 m, kesib olish masofasi,
- 4,8 km/soat, gruntni kesish tezligi
=20.67/6.35*0.2=16.27
ho‘s- 0.2 m, qatlam qalinligi,
tn – gruntni surishga ketgan vaqt,
= 40/1000*11,6=0,004
bu yerda
- 40 m, gruntni surish masofasi (ln = 10 ÷ 40)
- 11,6 mk/s, gruntni surish tezlishi
Vor- 14,1 km/s, orqaga qaytish tezligi,
tor - orqaga qaytish vaqti
=40/1000*14,1=0,003
Buldozerning bir ish smenasidagi ish unumdorligi
=795.8*8=6366.4m3/sm
Smenalar soni
V=2300*21*0.2*1.03*1.25=12437.25

So‘ngra FIK va ish vaqtini aniqlaymiz;
FIK =
Ish avqti t=F 0.98*8=7.84 coat


Avtosamosvallar yordamida chaqiqtoshni karyerdan tashish.
Avtosamosval markasininig – (VOLVO A35D) markalisini tanlaymiz va ish unumdorligini quyidagi formula orqali topamiz. m3/soat
Berilgan:
qa/c= 32,5 t avtosamosvalning yuk ko‘tara olish qobiliyati;
ρ= 1,8t/m3 qora chaqiqtoshning zichligi ;
L= 8km, qora chaqiqtoshni o‘rtacha tashish masofasi,
V= 40km/s, xarakatlanish tezligi;
tn= 0,35 soat, qora chaqiqtoshni avtosamosvalga yuklashga ketgan vaqt,
tp= 0,05 soat qora chaqiqtoshni to‘kishga ketgan vaqt,
= 0,75 ichki smenalik vaqtidan foydalanish koeffitsiyenti,
= 0,70 texnik unumdorlikdan ekspluatatsion unumdorlikka o‘tish koeffitsenti.
Avtosamosvalning bir ish smenasidagi ish unumdorligi
m3 /sm
Bir smenada talab etiladigan avtosamosvallar sonini aniqlaymiz
6366.4/94.8=67.1
Avtosamosvalning FIK ni aniqlaymiz;
FIK 67.1/68=0.98
Ish vaqti t = 8 • F = 0.98*8=7.9 soat,



Download 456.02 Kb.

Do'stlaringiz bilan baham:
1   ...   11   12   13   14   15   16   17   18   ...   31




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling