Tendering, Bidding, and Contract Traps 189
engineers,
drafting, and others. In the project as a whole, the
overall cost
is determined by identifying the number of hours of each group’s work
and the price is specified hourly, containing
any administrative expenses,
insurance, taxes, and other expenses.
The benefit from the contract per man-hours comes from the request of
the owner to change the part of the study design
or add another part that
is not in the scope of work that was delivered to the engineering office.
The additional cost can be calculated easily because the office provides a
number of hours for each
member and the price is known, so this provides
flexibility in the work as a whole.