Project Management in the Oil and Gas Industry
Impact on Increasing Cost
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
- Bu sahifa navigatsiya:
- 4.4.3 Project Late Impact
4.4.2 Impact on Increasing Cost
Sometimes the cost increases during the execution and there are many reasons for that. The most common cause is an increase in the price of materials from what was estimated before. There has been an increase in the foreign exchange rate, which often occurs in the machines that are imported from abroad. Another factor that increases cost is a difference in the quantities that have been executed and the quantities calculated from the drawings. An example that is common during excavation is that one can find different soil characteristics than what are in the soil report or the existence of problems in the soil were not taken into account, which requires restudying the soil and foundations with a change in the founda- tions design, which often causes an increase in costs. All of the above are project risks and if they occur they will eventually lead to an increase in project costs. Figure (4.7) presents the impact of increases in the project cost with respect to the owner. From this figure, one can find that the period of time to start the profit gain from the project is at the start of positive cash flow. Moreover, the total income from the project at the end of the project life- time is less than in the case of executing the project within the budget. 4.4.3 Project Late Impact In the case of a project delay rather than a delay in the time schedule of the project, which occurs with poor project management, the planner and the Figure 4.7 Effect of an increased cost on the whole project. Time Increase cost Cost, $ + – Maintenance & rehabilitation Operation Engineering phase Construction phase Start up 138 Project Management in the Oil and Gas Industry owner are often experienced in these matters and, therefore, those consid- erations are taken into account. A delay may also occur because of a bad choice made by the supplier or the delay could be beyond their control. No matter, the result is the same, and it is a delay in cash flow, as shown in Figure (4.8), resulting in an increased time period for the return. It is often the case that projects draw loans from banks as a result of this delay and increase the benefits. We find that the impact on profitability in end of the project lifetime may be more than in the case of only increased costs, as shown in Figure (4.8). Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling