Schedule baseline - A schedule baseline is the original project schedule — approved by the project team, sponsor, and stakeholders — by which performance is assessed. Schedule baselines are generally inflexible, though alteration of a schedule baseline via a formal change control process may be allowed.
Schedule compression technique - A schedule compression technique speeds up projects without affecting scope by decreasing the duration of a project’s critical path. There are two main schedule compression techniques: crashing and fast tracking. (See also duration compression)
Schedule model - A logically arranged, time-based plan for project activities. It is used to create a project schedule.