To-Complete Performance Index (TCPI) - A project’s to-complete performance index is the cost performance it needs to achieve to be completed within budget. The TCPI is calculated as the ratio of work remaining to budget remaining.
Tolerance - The acceptable level of variance in project performance. The project sponsor is typically informed if tolerance levels are crossed.
Top-Down estimating - Top-Down estimating uses historical data from similar projects to compute time and cost estimates. (See also analogous estimating)
Total cost of ownership (TCO) - The total cost of ownership estimates the sum total of direct and indirect costs incurred in the purchase, operation, and maintenance of an asset through its life.
Total float - The length of time an activity can be delayed from its early start date without affecting the project end date.
Trigger condition - A condition that causes a risk to occur. Trigger conditions can serve as warning signs that risks have occurred or are about to occur. (See also risk trigger)