7.4
Implementing Mitigation: Planning, Management and 
Monitoring 
The mitigation measures applied to reduce significant impacts will require a number of 
management plans to detail the implementation and action items needed as well as 
monitoring and reporting requirements to ensure compliance and measure performance.
7.4.1 
Design 
The following outline the mitigation requirements during design phase: 
 
Integration of design mitigation into WTG design related to lighting design and 
specifications, painting specifications, and exclusion of roosting and perching 
opportunities.
7.4.2 
Pre-Construction 
The following outline the mitigation requirements pre-construction: 
 
Review of Construction Methodology and Schedule by environmental consultant, 
especially in regards to: 
Site Clearance and Layout 
Timing and method of emissions-generating works
Lighting Strategy 
Solid Waste Management Strategy
 
Preparation of Biodiversity Action Plan, inclusive of Species- specific Action Plans 
which outlines the CHA process, findings and illustriates the pathway to no-net loss 
 
Preparation of Reptile Relocation Methodology 
 
Preparation of Flora Conservation Action Plan 
 
Preparation of Breeding Bird Protection Plan 
 
Carry out preconstruction surveys and implementation of actions as per the above 
plans 
 
Preparation of CEMP, inclusive of: 
General Site Controls 
Solid Waste Control Plan 
Chance Find Procedure 
Air Quality Control Plan 


Dzhankeldy 500MW Wind Farm 
ESIA Volume 2- Main Text, Tables & Figures 
283 
Dust Control Plan 
Noise Control Plan 
Lighting Control Plan 
Hazardous Materials Control Plan 
Emergency Action Plans 
Spill Prevention and Clean-up Procedures 
7.4.3 
Construction 
The following outline the mitigation requirements during construction: 
 
The EPC will employ a full-time site-based Ecologist and, during active periods, a 
Herpetologist, to ensure that ecology related measures are understood and fully 
implemented.
 
Implementation of CEMP 
Daily Checklist
Weekly Inspection 
Monthly Reporting 
Quarterly Auditing 
 
Biodiversity Monitoring and Evaluation Programme BMEP for ongoing monitoring of 
translocation/relocation success, chance find procedures, target species impacts, 
etc. 
7.4.4 
Post Construction 
The following outline the mitigation requirements post-construction: 
 
Preparation of Restoration Action Plan 
 
Carrying out restoration works 
 
Post-restoration survey 
 
Compensation Offset Plan (for Habitat & Flora) 
 
Habitat restoration offset works 
 
Biodiversity Monitoring and Evaluation Programme BMEP
7.4.5 
Operation 
The following outline the mitigation requirements during operation: 
 
Preparation and Implementation of OEMP, inclusive of: 
General Site Controls 
Noise Control Plan 
Lighting Control Plan 
Chance Find Procedure 


Dzhankeldy 500MW Wind Farm 
ESIA Volume 2- Main Text, Tables & Figures 
284 
Fatality Monitoring Plan 
Collision Risk Management Plan which includes PBR thresholds, proposed SDOD 
mechanism and Cut-in Curtailment criteria.
Compensation Offset Plan (for Birds & Bats). 
 
Compliance checks and reporting include: 
Daily Checklist
Weekly Inspection 
Monthly Reporting 
Quarterly Auditing 
 
Biodiversity Monitoring and Evaluation Programme BMEP
 
 

Download 6.64 Mb.

Do'stlaringiz bilan baham:
1   ...   195   196   197   198   199   200   201   202   203




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling