354
POWER PLANT ENGINEERING
Medium Head Plants. If the head of water available is more than 50 m.,
then the water from the
forebay is conveyed to the turbines through pen-stocks. Such a plant will then be named as a medium
head plant.
In these plants, the river water is usually tapped off to a forebay on one bank of the river as
in the case of a low head plant. From the forebay, the water is then led to the turbines through penstocks.
Such a layout is shown in Fig. 11.8.
River
Dam
Head Gate
Canal
Forebay
Power
House
Ta
il R
ac
e
Fig. 11.7
Head Race
Open Canal
Forebay
Bed
River
Turbine
Tail Race
Penstock