Document Outline - Cover
- Title Page
- Copyright Page
- Dedication
- Contents
- Preface
- About the Author
- 1 How to Manage Oil and Gas Projects
- 1.1 The Principal of Project Management
- 1.2 Project Characteristics
- 1.3 Project Life Cycle
- 1.3.1 Initiation of the Project
- 1.3.1.1 Getting to the Scope Baseline
- 1.3.2 Feasibility Study
- 1.3.3 FEED (Preliminary) Engineering
- 1.3.4 Detail Engineering
- 1.3.5 Decision Support Package
- 1.3.6 Design Management
- 1.3.7 Execution Phase
- 1.3.8 Commissioning and Startup
- 1.4 Is this Project Successful?
- 1.4.1 Project Management Goals
- 1.4.1.1 Project Integration Management
- 1.4.1.2 Project Scope Management
- 1.4.1.3 Project Time Management
- 1.4.1.4 Project Cost Management
- 1.4.1.5 Project Quality Management
- 1.4.1.6 Project Human Resource Management
- 1.4.1.7 Project Communications Management
- 1.4.1.8 Project Risk Management
- 1.4.1.9 Project Procurement Management
- 1.5 Project Management Tasks
- 1.5.1 Define the Project Target
- 1.5.2 Define the Scope of Work
- 1.5.3 Define the Time Frame
- 1.5.4 Define the Available Resources
- 1.5.5 Define the Cost
- 1.5.6 Evaluate the Master Plan
- 1.5.7 Accept the Master Plan
- 1.5.8 Schedule Follow Up
- 1.5.9 Cost Follow Up
- 1.5.10 Comparing Between Actual Work and Master Plan Cost
- 1.5.11 Performance Evaluation
- 1.6 Project Manager Skill
- Quiz
- 2 Project Economic Analysis
- 2.1 Introduction
- 2.2 Project Cash Flow
- 2.2.1 Depreciation Methods
- 2.2.1.1 Straight-Line Method
- 2.2.1.2 Declining-Balance Method
- 2.2.1.3 Sum-of-the-Year-Digits
- 2.2.1.4 Sinking-Fund Method
- 2.2.1.5 Service-Out Method
- 2.2.2 Method of Net Present Value (NPV)
- 2.2.3 Minimum Internal Rate of Return (MIRR)
- 2.2.4 Payout Method
- 2.3 Economic Risk Assessment
- 2.3.1 Probability Theory
- 2.3.2 Probability Distribution of Variables
- 2.3.2.1 Normal Distribution
- 2.3.2.2 Log Normal Distribution
- 2.3.2.3 Binominal Distribution
- 2.3.2.4 Poisson Distribution
- 2.3.2.5 Exponential Distribution
- 2.3.2.6 Weibull Distribution (Rayleigh Distribution)
- 2.3.2.7 Gamma Distribution
- 2.3.2.8 Logistic Distribution
- 2.3.2.9 Extreme Value (Gumbel Distribution)
- 2.3.2.10 Pareto Distribution
- 2.3.3 Distribution for Uncertainty Parameters
- 2.3.3.1 Triangular Distribution
- 2.3.3.2 Uniform Distribution
- 2.3.4 Choose the Appropriate Probability Distribution
- 2.3.4.1 Chai Square Method
- 2.3.4.2 Kolmograv-Smirnov (K-S)
- 2.4 Decision Tree
- 2.5 Monte-Carlo Simulation Technique
- 2.6 Risk Adjusted Value (RAV)
- 3 Pitfalls in Time Schedule Planning
- 3.1 Introduction
- 3.1.1 Plan Single Point of Accountability (SPA)
- 3.1.2 Starting the Plan
- 3.1.3 Work Breakdown Structure (WBS)
- 3.2 Responsibilities of the Team
- 3.3 Expected Activity Time Period
- 3.4 Calculate the Activity Time Period
- 3.5 Time Schedule Preparation
- 3.5.1 Gantt Chart
- 3.5.2 Arrow Diagram Method (ADM)
- 3.5.3 Precedence Diagram Method (PDM)
- 3.5.4 Critical Path Method (CPM)
- 3.5.5 Program Evaluation and Review Technique (PERT)
- 3.5.6 Example
- 3.5.7 Application of the PERT Method
- 3.5.7.1 Statistics Calculation for Activity Time
- 3.5.7.2 Example
- 3.5.7.3 Time schedule control
- 3.6 Planning Overview
- Quiz
- 4 Project Cost Control
- 4.1 Introduction
- 4.2 Cost Types
- 4.2.1 Cost Estimate
- 4.2.1.1 Top-Down Estimates
- 4.2.1.2 Bottom-Up Estimates
- 4.2.1.3 Analogous Estimates
- 4.2.1.4 Parametric Estimates
- 4.2.2 Steel Structure Cost Estimate
- 4.2.3 Detailed Cost
- 4.2.4 Cost Estimate to Project Control
- 4.3 Economic Analysis to Project Cost
- 4.3.1 Work Breakdown Structure (WBS)
- 4.3.2 Organization Breakdown Structure (OBS)
- 4.3.3 OBS/WBS Matrix
- 4.3.4 Work Packages
- 4.3.5 Cost Control
- 4.3.6 (S) Curve
- 4.3.7 Engineering Cost Control
- 4.4 Cash Flow Calculation
- 4.4.1 Project Cash Flow
- 4.4.2 Impact on Increasing Cost
- 4.4.3 Project Late Impact
- 4.4.4 Impact of Operation Efficiency
- Quiz
- 5 Resource Hiring
- 5.1 Introduction
- 5.2 Project Organization
- 5.2.1 Types of Organizations
- 5.2.1.1 Project Organization as a Part of the Company
- 5.2.1.2 Separate Project Organization
- 5.2.1.3 Matrix Organization
- 5.2.2 Selecting the Best Organization
- 5.3 Roles and Responsibilities of the Project Manager
- 5.3.1 Project Manager as a Leader
- 5.4 Administrative Organization for Total Quality Management
- 5.5 Team Member Selection
- 5.6 Managing the Team
- 5.7 Allocate Resources to Project Plan
- 5.8 Relation Between Project Parties
- 5.9 Document and Information Transfer
- 5.10 Information Transfer
- 5.11 Quality Control in the Design Phase
- 5.11.1 Inputs and Outputs of the Design Phase
- 5.11.2 Design Verification
- 5.11.3 Change in the Design
- 5.11.4 Approval of the Design
- Quiz
- 6 Tendering, Bidding, and Contract Traps
- 6.1 Introduction
- 6.2 Contracts
- 6.2.1 Measured Contract
- 6.2.2 Lump Sum
- 6.2.3 Cost Plus
- 6.3 Contract Between the Owner and Engineering Office
- 6.4 The Importance of Contracts in Assuring the Quality of the Project
- 6.5 Contracts in ISO
- 6.6 FIDIC Contracts
- 6.7 General Conditions in the Contracts
- 6.8 Arbitration and the Arbitrator
- 6.9 Bids and Tenders
- 6.9.1 Public (Open) Tender
- 6.9.2 Limited Tender
- 6.9.3 Negotiated Tender
- 6.9.4 Direct Order
- 6.9.5 Tender Technical Evaluation
- 6.9.6 Commercial Evaluation
- 6.9.6.1 Commercial Evaluation Methods
- 6.10 Closeout Report
- Quiz
- 7 New Approach in Managing Oil and Gas Projects
- 7.1 Introduction
- 7.2 Quality System
- 7.3 ISO 9000
- 7.4 Quality Management Requirements
- 7.4.1 Quality Manual
- 7.4.2 Quality Plan
- 7.4.3 Quality Control
- 7.4.3.1 Why is Quality Control Important?
- 7.4.3.2 Submittal Data
- 7.4.3.3 How to Check Incoming Materials
- 7.4.3.4 Methods of Laying Out and Checking Work
- 7.4.3.5 Material/Equipment Compliance Tests
- 7.4.3.6 When to Inspect Work
- 7.4.3.7 Paperwork/Documentation
- 7.4.3.8 Quality Control Plans
- 7.4.4 Quality Assurance
- 7.4.4.1 Quality Assurance in the ISO
- 7.4.4.2 The Responsibility of the Contractor (Manufacturer)
- 7.4.4.3 Responsibility of the Owner
- 7.5 Project Quality Control in Various Stages
- 7.5.1 Feasibility Study Stage
- 7.5.2 Feed (Preliminary) Engineering
- 7.5.3 Detailed Engineering Study
- 7.5.3.1 Design Quality Control
- 7.5.4 Execution Phase
- 7.5.4.1 ISO and Control Work
- 7.5.4.2 Inspection Procedures
- 7.5.4.3 Importance of Contracts in Assuring the Project Quality
- 7.5.4.4 Checklists
- 7.6 Operational Phase of the Project
- 7.7 Total Building Commissioning System
- 7.7.1 Planning Stage
- 7.7.1.1 Identify Commissioning Team
- 7.7.1.2 Define Owner’s Project Requirements with the Customer Agency
- 7.7.1.3 Develop Preliminary Commissioning Plan
- 7.7.1.4 Commissioning for Certifications (LEED, Energy Star, etc.)
- 7.7.1.5 Commissioning Agent Costs
- 7.7.1.6 Cost-Benefit Analysis for Commissioning
- 7.7.2 Design Stage
- 7.7.2.1 Incorporate Commissioning into A/E and CM Scope of Services
- 7.7.3 Construction Stage
- 7.7.3.1 Review Submittals for Performance Parameters
- 7.7.3.2 Develop and Utilize Construction Checklists
- 7.7.3.3 Oversee and Document Functional Performance Testing
- 7.7.3.4 Test Data Records
- 7.7.3.5 Hold Commissioning Team Meetings and Report Progress
- 7.7.3.6 Conduct Owner Training
- 7.7.3.7 Turnover Commissioning Record
- 7.7.4 Building Commissioning Process Post-Construction Stage
- 7.7.4.1 Post-Construction Stage
- 7.7.4.2 Perform Deferred and Seasonal Testing
- 7.7.4.3 Re-inspect/Review Performance Before End of Warranty Period
- 7.7.4.4 Complete Final Commissioning Report
- 7.7.4.5 Recommission Facility Every 3–5 Years
- 7.7.4.6 Recommissioning
- 7.7.5 Advantages for Total Building Commissioning System
- Quiz
- 8 Practical Risk Management for Oil and Gas Projects
- 8.1 Introduction
- 8.1.1 The Risk Management Process
- 8.2 Project Risks
- 8.3 Risk Assessment
- 8.4 Risk Identification
- 8.4.1 Methods of Defining Risk
- 8.4.1.1 Brainstorming
- 8.4.1.2 Delphi Technique
- 8.4.1.3 Nominal Group Technique
- 8.4.1.4 Crawford Slip
- 8.4.1.5 Expert Interviews
- 8.4.1.6 Root Cause Identification
- 8.4.1.7 Checklists
- 8.4.1.8 Documentation Reviews
- 8.4.2 Grouping the Risks
- 8.5 Define Priorities
- 8.5.1 Matrix Method
- 8.5.2 Tabulated Method
- 8.6 Risk Response Planning and Strategies
- 8.7 Risk Monitoring and Control
- 8.8 Example
- 8.9 Operations risk
- 8.10 Methods of Risk Avoidance
- Quiz
- References
- EULA
Do'stlaringiz bilan baham: |