How to Manage Oil and Gas Projects 29
1.5.8 Schedule Follow Up
After all the previous steps, the execution phase will start. Then, start track-
ing the progress of work by registering the amount of work done and the
used resources. This will apply to the activities that took place as well as the
activities under the operation.
Follow-up schedules are adjusted periodically
in order to be commen-
surate with the actual on site. We must, therefore, do the follow-up peri-
odically and as agreed upon at the beginning of the project.
1.5.9 Cost Follow Up
You should follow-up on the cost periodically during an agreed
period of
time to track the project cost and compare it to the estimated cost of the
project that was identified through the budget and approved by the owner.
We must follow the paid cost and the cost that is due to others with the
time of the purchase orders and contracts of employment. Any deviation
gives a snapshot of the position to evaluate the
deviations at the same time,
and then we can expect the total cost at the end of the project.