Project Management in the Oil and Gas Industry
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
- Bu sahifa navigatsiya:
- Table 4.6.
- Table 4.7
- March During this month, the work is close to reaching the plan. Now the time schedule is not the only problem but also the cost increase. April
- 4.3.7 Engineering Cost Control
Days
C ost, K 14 15 16 17 18 19 20 21 22 23 24 25 Figure 4.4 Cash flow in case of late date. 40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Days C ost, K 14 15 16 17 18 19 20 21 22 23 24 25 Figure 4.5 Cash flow envelope. 35 30 25 20 15 10 5 0 1 Ahead of schedule Within of schedule Behind of schedule 2 3 4 5 6 7 8 9 10 Days C ost, K 11 12 13 14 15 16 17 18 Project Cost Control 133 When the cost curve could prevent this cost within the envelope, this indicates that you are in accordance with the scheme called the time “within schedule.” Where the curve is less than planned, as shown in Figure (4.4), the situ- ation is critical as the project is late and considered “behind schedule.” As an example, the following table gives the values of the cost of plan- ning in an engineering project for a period of twelve months in accordance Table 4.6. Cost per month. June May April March Feb. Jan. Plan 200 200 200 200 140 60 Work in month 1000 800 600 400 200 60 Cumulative 20000 20000 20000 20000 14000 6000 Cost/month 100000 80000 60000 40000 20000 6000 BCWS Dec. Nov. Oct. Sep. Aug. July Plan 100 100 200 200 200 200 Work in month 2000 1900 1800 1600 1400 1200 Cumulative 100000 10000 20000 20000 20000 20000 Cost/month 200000 19000 18000 16000 14000 120000 BCWS Table 4.7 Parameters calculation. June May April March Feb. Jan. 20000 20000 20000 20000 14000 6000 Cost per month 100000 80000 60000 40000 20000 6000 BCWS 20000 20000 20000 20000 14000 4000 BCWP (EV) 20000 21000 23000 22000 14000 4000 ACWP 98000 78000 88000 38000 18000 4000 EV cumulative 104000 84000 63000 40000 18000 4000 ACWP cumulative 2000 2000 1000 1000 0 0 CV 0 0 0 100 200 200 SV 0.942 0.929 0.921 0.95 1 1 Cost index 1 1 1 0.95 0.9 0.66 Schedule index 15000 15000 15000 15000 15000 15000 BAC 16000 16250 16333 16034 15000 15000 EAC 134 Project Management in the Oil and Gas Industry with the planning timetable explained above. In the project six months after the transaction, we will calculate the position of the crisis to see the project as presented in Table (4.6). From the previous table calculate the cost control parameters after six months from start of the project. From the parameters in Table (4.7), provide us tools to evaluate the proj- ect every month as follows: January The cost of execution is 300 less than the ACWP in this month, so the work is slow but the cost is acceptable. The reason for this may be due to late hiring of new labours. February The work is progressing as planned, but work is still slow. Deal with this situation by letting them work on weekends to achieve the required time schedule. March During this month, the work is close to reaching the plan. Now the time schedule is not the only problem but also the cost increase. April This month the work was done more than it was planned. Now the work is going according to schedule and will be back to a normal mode of work, avoiding work on weekends. May The activity increased slightly more than planned, so we are going with the time schedule. June The work is progressing according to plan after six months of the project. Work is proceeding according to schedule, but there has been an increase in cost. It is expected that the budget at the end of the project will be about $16,000. 4.3.7 Engineering Cost Control The most the project engineering phase has is ten percent of the cost of the total project. It is worth mentioning that most of the cost in design and drafting is around 58 percent of the total engineering cost. Table (2.8) Project Cost Control 135 presents the breakdown of the engineering phase cost. The engineering contractors fee or the administration overhead and profit cost usually aver- age five percent. It is shown in Table (2.8) that design and drafting are the most significant items of technical man hour cost, so, in most cases, it is easier to calculate the required design and drafting cost and then develop the other item as a percentage. Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling