Project Management in the Oil and Gas Industry
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
- Bu sahifa navigatsiya:
- 8.5.1 Matrix Method
8.5 Define
Priorities There are many ways to define the risk ranking for each risk item that was defined before. In this step, the facilitator will ask the team in the meeting to define the degree of likelihood that the event will occur and, also, define how much it can impact the project. There are two traditional methods. The matrix method is the most popular and is defined in the PMOBOK guide. The other way depends on ranking the risks in a table and defining them in three categories: red, yellow, and green for every identified risk. 8.5.1 Matrix Method In the previous meeting everyone wrote down all expected risks. Now you want to determine the priorities of those risks. We will use this experi- ence in assessing the risk at the same meeting and there will be a two-stage evaluation process. The first phase requires determining the likelihood of a risk and rating it from one to nine, one being the least likelihood of the event occurring and nine being the greatest probability of the event occurring. In the second stage, the team determines the outcome of an event on the project or the expected losses due to this event occurring and it is divided into the following cases: • High: It has a greater significant impact on the time schedule or the cost of the project. • Medium: It has a medium impact on the time schedule and cost. • Low: It has a lower influence on the time schedule and little impact on the cost. In summary, the following table can be used to determine the risk priorities. The team must know what the probability of the event occurring is and what its impact is to the project. The impact will be obtained through the The History of Graphene 303 discussion for each event by answering the two questions: What is the probability of potential risks and what is their impact on the project? From the previous matrix shown in Table 8.2, one can determine the risk category. In the case of an unacceptable risk, the event needs to be analysed with high accuracy and a thorough examination or by focusing on finding solu- tions to them. If their occurrence will cause failure for the whole project and the project cannot be done as planned, the risks are unacceptable and must be resolved now. In the case of high-risk, this situation occurs when the event could have a significant impact on the project schedule and cost. Therefore, sustained monitoring is required. In the case that a medium-risk event occurs, medium impact is expected and not all the key points of the project will be affected. Therefore, the risk mitigation must be reviewed at each meeting of the project and evaluate their action work and follow it up periodically. In case of a low-risk event, it is not expected at the time of the event to have a significant impact on the project and must follow up from time to time. The risks that have been assessed as high risk at the follow-up may cause some changes due to some work or actions performed, which can reduce or increase of the probability of the event occurring. After identifying the risks, rank them from highest to lowest risk. In every item, find a solution and accurately identify the responsibilities as to who will do the activity. This will reduce the risk of the event and it will be registered, as shown in Table 8.3. Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling