Pitfalls in Time Schedule Planning 105
to 44000 man hours. Noting that man hours reflects to money, the cost is
around,
for this project, two million USD. As if you have a high fee rate per
man-hour, the man-hour may be reduced to less than above. It depends on
how the engineering firm approaches their proposal as some engineering
firms reduce the number of man-hours and
increase the cost per man-
hour and vice versa according to their strategy and the market share in this
time period.
The progress of an engineering activity is required to be identified for
control, so you should put some basics to control.
If the engineering firm
will do the work, the progress measurement should be identified and be
agreed upon by the client and the engineering firm
before starting the proj-
ect. For example, in a case of study reports, the following is an example for
the progress measured as shown in Table 3.7.
For different engineering
discipline activities, the measured progress
should be defined. As in oil and gas projects, preparation of P& ID is very
23.31
26.0