Project Management in the Oil and Gas Industry
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
- Bu sahifa navigatsiya:
- Table 3.4
- Frequency Time Figure 3.10
T T T T a o m p 4 6 , (3.1) where T a is average time, T o is optimistic time, T p is pessimistic time, and T m is most likely time. Pitfalls in Time Schedule Planning 103 3.5.7.2 Example For the previous example of constructing the concrete foundation, there are three values for time for each activity, as shown in the following table. After defining the critical path from the previous example, calculate the expected time at each activity as shown in Equation 3.1. Calculate the standard deviation using the following equation: s T T P o 6 (3.2) Variance, V, is S 2 . From Table 3.5 calculate the Ta, which is the average time and the stan- dard deviation based on Equations 3.1 and 3.2, respectively. The variance Table 3.4 PERT example. To Tm Tp Activity Item 1 3 5 Mobilization 1 6 8 11 Excavation 2 8 16 25 (Pouring concrete foundation and piping support) 3 3 4 5 Install the piping 4 1 1 2 Install the mechanical package 5 1 1 3 Put the grouting 6 2 5 7 Connect the piping 7 1 1 2 Commissioning and start up 8 T o T p T m T a Frequency Time Figure 3.10 Probability distribution for every distribution. 104 Project Management in the Oil and Gas Industry is calculated as it is only possible to sum the variance. You cannot perform summation for the standard deviation. The minimum time to finish the project is eighteen days and the maximum time to finish is 39 days. The average time period to finish the project is in 23.31 days. What is the probability if you increase the project time over 25 days? This value can be calculated from the following equation: V = 0.44 + 0.694 + 1.36 + 0.028 + 0.11 + 0.11 = 2.74 days. Standard deviation (S) is 1.66 days. z 26 23 31 1 66 1 62 . . . From the probability distribution tables, the probability that the project completion period is more than 26 days is five percent. The probability that the execution time for the project is equal to or less than 26 days is 95 percent, as shown in Figure 3.11. 3.5.7.3 Time schedule control For real projects, four legs platforms in a water depth around 80 m, the percentage of hours of different disciplines will be as follows in Table (3.6) as a guideline: The approximate man hours for structure engineering activities is about 5600–6300 man hours, whereas the total project man hour is about 38000 Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling