Secondary risk - A risk created by a risk response.

Security - Security in project management refers broadly to protecting humans, information, and resources from risk.

Six Sigma - An approach to process management that focuses on the near total elimination of product or service defects. It uses quality management methods to improve and optimize processes involved in the production of a product or service so that 99.99966 percent of process outcomes are defect-free.

Slack time - The length of time an activity's early start can be delayed without affecting project duration. (See also float)

Slip chart - A slip chart graphically compares predicted activity completion dates with originally planned completion dates.

Slippage - The negative variance between planned and actual activity completion dates. Slippage may also refer to the general tendency of a project to be delayed beyond planned completion dates.

Soft project - A soft project does not have a physical output.


Download 63.25 Kb.

Do'stlaringiz bilan baham:
1   ...   109   110   111   112   113   114   115   116   ...   127




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling