Path convergence - On a schedule network diagram, path convergence occurs when an activity has multiple predecessors.
Path divergence - On a schedule network diagram, path divergence occurs when an activity has multiple successors.
Percent complete - The percent complete indicates the amount of work completed on an activity as a percentage of the total amount of work required.
Performance measurement baseline - A performance measurement baseline uses the schedule, cost, and scope baselines to create a point of comparison by which project performance is assessed. Variance from the performance measurement baseline may prompt corrective action.