Project Charter: Menu Tablets date: 07-07-23


Download 194.43 Kb.
Sana25.08.2023
Hajmi194.43 Kb.
#1670339
Bog'liq
1. Activity-Project-Charter




Project Charter: Menu Tablets

DATE: 07-07-23





Project Summary

This project aims to introduce guest facing digital menus in the form of menu tablets that will reduce customer wait times (thus improving quality of service) as well as potentially reduce food waste and increase the number of customers served per day. The project will be piloted in two locations at the bar areas.




Project Goals

  • Improve customer experience & reduce the number of negative customer reviews by TBD amount by TBD

  • Increase appetizer sales by 15% average overall, with the North location targeted for a 10% increase and the Downtown location targeted for a 20% increase.

  • Increase average check total to $75 by selling more appetizers and beverages by the end of Q2, resulting in increased profits

  • Increase product mix

  • Decrease table turn time by 30 minutes

  • Decrease employee burnout and turnover by TBD amount by TBD

  • Cut food waste by 25%

  • Increase daily guest counts by 10%




Deliverables

  • Tablets installed in the bar area of two restaurant locations

  • A plan to train the staff on the new system

  • Clear data points to track metrics

  • Updated website and menu design

  • Reduction in food waste

  • Decrease table turn time




Scope and Exclusion

In-Scope:



Out-of-Scope:

  • Adjustment of the policy on order returns to due error as part of the tablet rollout




Benefits & Costs

Benefits:

  • Increase appetizer sales by 15% average overall

  • Increase in average check to 75$

  • Cut food waste by 25%

  • Increase daily guest counts by 10%



Costs:

  • Training materials and fees of $10,000

  • Hardware and Software Implementation across locations $30,000

  • Maintenance (IT fees through EoY) $5,000

  • Updated website and menu design fee $5,000

  • Other customization fees $550




Appendix:

  1. Removal of decreasing guest wait time as a separate goal

    • Decided between Peta, Alex, and Gilly that it can be removed given Deanna’s approval.

  2. Reallocating payroll

    • Decided that Peta would think through how to account for increase in demand of line-cooks and bussers and runners and revert on a solution.

  3. Revise the food waste goal to include metrics that better capture kitchen staff’s performance

    • Mentioned as a possibility by Peta. Yet to be addressed as to whether it will be included in the project scope or not

  4. Adjustment of the policy on order returns to due error as part of the tablet rollout

    • Decided between Carter, Peta, Deanna, and Gilly to be kept out of the project scope

  5. Satisfaction of the kitchen staff as a project goal

    • Decided between Carter and Peta that it can be included once Carter provides specific metrics to measure staff satisfaction.