B. The Work Plan
Table 6.3 Work plan score.
No. of points
Item
50
50
75
50
25
50
100
1. Submittal of the tender in compliance with the terms and
conditions listed
in the tender document
2. Submittal of the tender in compliance with the technical
requirement described in the tender document
3. Adequacy of the man months indicated in the proposal to
execute
the required services
4. Tender’s proposed project time schedule and description of
the approach to completeness of the work
5. Tender’s localization plan to submit a complete program
describing the components of
the equipment that would be
manufactured locally
6. Adequacy of the quality assurance program
7. Tender’s organization chart and adequate manpower data
of tender’s personnel to be assigned
during the execution of
the work to meet the tender’s schedule
400
Sub total