Pitfalls in Time Schedule Planning 107
For overall project progress, the following measurements in Table 3.11
can be considered as a guide line.
3.6 Planning
Overview
The following steps are important to obtaining the schedule plan:
•
Create the project definition.
The project manager and the
project team develop the statement of requirements (SOR),
which identifies the purpose, scope, and deliverables for the
project and defines the responsibilities of the project team.
•
Develop a risk management strategy. The project team evalu-
ates the likely obstacles and constrains and creates a strategy
for
achieving the required costs, schedule, and quality.
•
Build a work breakdown structure.
The team identifies all the
tasks required to build the specified deliverables. The scope
statement and project purpose help to define the boundaries
of the project.
•
Identify task relationships.
The detailed tasks, known as work
packages, are placed in the proper sequences.
Table 3.10 Manufacturing delivery progress measuring guideline.
Manufacturing and delivery milestone
Equipment Bulk materials
All vendor drawings
and vendor data approved
10%
All sub- ordered materials received by vendor
25%
10%
Materials successfully inspected,
tested and
accepted
50%
75%
All materials delivered on site
15%
15%