106
Project Management
in the Oil and Gas Industry
critical, so the most practical progress measurement will be as follows in
Table 3.8.
For procurement services, the following Table 3.9
presents the tradi-
tional progress for measuring percentages.
The requisition of bulk materials like steel structure, piping, electrical
cables, or others is based on the material take offs (MTO) and, in most
cases, it will be issued in three MTOs. The
following weights are to be
applied for bulk MTO:
First MTO requisition 65%
Second MTO requisition 25%
Third and final MTO requisitions 10%
For the equipment delivery, mile stone progress will use as Table 3.10 as a
guideline. It defines the percentage progress after finishing the mile stones.
Table 3.7 Engineering report progress measurement guideline.
Activity Progress
percentage
Issue
draft to the client
30%
Completed document
review by the client
50%
Incorporate the client comments
80%
Final
report approval
100%
Table 3.8 Engineering preparation for P&ID.
Activity
Progress percentage
Study and prepare draft or sketches
20%
Completed document review by the client
60%
Issue for design
75%
Issued for construction finally without hold
100%