Pitfalls in Time Schedule Planning 97
network with the total durations shorter than the
critical path is called a
sub-critical or non-critical path.
3.5.5 Program Evaluation and Review Technique (PERT)
This is required in any case of special projects or large-scale deliveries
with a variety of activities. All activities in the project need to be identified
accurately and all must be completed before the project completion. These
activities must be initiated and carried out in a
specific sequence and must
be completed before the start of the completion of other activities. Some
activities may occur in parallel, meaning that two or more could be com-
pleted at the same time.
In
addition, there are specific achievements that indicate the completion
of key stages in the project. The successful management of such projects
must be carefully planned during implementation of these
projects to
speed up the delivery during a specified period of time, to coordinate the
multi-activity of the project and monitor the use
of various resources nec-
essary for its implementation, and to achieve the project on time within
the budget cost.
One of the
operations research methods, which are used to assist the plan-
ning team, the coordination, the control of such projects
special in case of the
multiplicity and complexity of activities, and large size projects is known as
the method of Program Evaluation and Review Technique known as PERT.
Although the method of PERT is mainly
used for military purposes, it
has been used successfully since 1959 for most large-scale projects. PERT