96
Project Management in the Oil and Gas Industry
3.5.3 Precedence Diagram Method (PDM)
This method is the most common one.
In this method, every activity is
presented by a box or a rectangle, as shown in Figure 3.5,
and the detail of
the rectangle is shown in Figure 3.6. The rectangles are connected by the
arrows which represent the dependencies between the activities. From this
figure, it is clear that activity C starts after activities D and B.
Figure 3.6 presents
the inside of a rectangle, which will note the dura-
tion, early start time (ES), early finish (EF) time, and also the latest start
(LS) and latest finish (LF) time.
3.5.4 Critical Path Method (CPM)
The essential technique for using CPM is to establish
a model of the project
that includes a list of all activities required to complete the project, the time
duration that each activity
will take to completion, and the dependencies
between the activities.
By using these values, CPM calculates the longest
path of planned activ-
ities to the end of the project and the earliest and latest time that each
activity can start and finish without making the project take a longer time.
This process determines which activities are “critical,” which are the
activities
on the longest path, and which have “total float,” as these activi-
ties can be delayed without making the project longer.
Any delay of an activity on the critical path directly impacts the planned
project completion date (i.e. there is no float on the critical path).
A project
can have several critical paths. An additional parallel path through the
Do'stlaringiz bilan baham: