Finish-To-Finish - In a finish-to-finish relationship, a successor activity cannot finish until a predecessor activity has finished.

Fishbone diagram - A fishbone diagram is used in project management to identify and categorize the possible causes of an effect. (See also Ishikawa diagram)

Fixed duration - A task in which the time required for completion is fixed.

Fixed formula method - The fixed formula method calculates earned value in a given period of time by splitting a work package budget between the start and completion milestones of a work package. A known proportion of value is earned upon beginning the work package, and the rest is earned upon completing the work package.


Download 63.25 Kb.

Do'stlaringiz bilan baham:
1   ...   39   40   41   42   43   44   45   46   ...   127




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling