III.Mehnat sarfi va mshinani ishlash vaqti sarfining kalkulatsiyasi va ishlab chiqarish grafigini tuzish.
Asos
ШНК bo`yicha
|
Ishlarning nomi
|
Ishlarning hajmi
|
Mehnat sarfi
|
Mashina ishlash vaqtining sarfi.
|
izoh
|
O`lchov birligi.
|
Miqdor
|
Mahsulot birligi uchun, kishi-soat
|
Butun hajm uchun, kis-soat
|
Mahsulot birligi uchun, mash-soat
|
Butun hajm uchun, mash-soat
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
4.01.02-04
Jadval
1.01-030-14
|
Buldozer yordamida o`simlik qatlamini qirqib olish.
|
1000m3
|
1.075
|
5.93
|
6.37
|
5.93
|
6.37
|
|
-
|
O`simlik qatlamini tashish (tashqariga chiqarish)
|
1000m3
|
1.075
|
17.79
|
19.12
|
17.79
|
19.12
|
|
4.01.02-04
Jadval
1.01-014-02
|
Kotlovanda ekskavator orqali grunt qazish
|
1000m3
|
2.825
|
60.20
|
170.065
|
60.20
|
170.065
|
|
-
|
Gruntni tashish (tashqariga chiqarish)
|
1000m3
|
2.825
|
180.60
|
510.195
|
180.60
|
510.195
|
|
4.01.02-04
Jadval
1.01-005-10
|
Transheyada ekskavator orqali grunt qazish
|
1000m3
|
3.195
|
9.20
|
29.394
|
9.20
|
29.394
|
|
4.01.02-04
Jadval
1.01-014-03
|
Bulldozer yordamida kotlovandagi qoldiq gruntga ishlov berish
|
1000m3
|
2.825
|
14.30
|
40.398
|
14.30
|
40.398
|
|
4.01.02-04
Jadval
1.02-057-03
|
Qo`l yordamida transheyada gruntga ishlov berish
|
100m3
|
0.441
|
154,0
|
67.914
|
-
|
-
|
|
|
|
|
|
|
|
|
775.542
|
|
Ishlarni bajarish kalendarniy grafigi.
Ishlarning nomi
|
Ishlarning hajmi
|
Ishlarning mehnat srfi Q, kishi -kun
|
Qabul qilingan mashinalar
|
Sutkadagi smenalar soni, m
|
Smenadagi ishchilar soni, n
|
Sutkadagi brigada tarkibi m*n
|
Meyor (norma)ni bajarish koeefitsienti K
|
Ishlarning loyihaviy davomiyligi, T
|
Ishchi kunlar
|
O`lchov birligi
|
Miqdori
|
Nomlami-shi
|
Mash.-sm.lar miqdori
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
11
|
12
|
Buldozer yordamida o`simlik qatlamini qirqib olish
|
1000m3
|
1,075
|
0.78
|
Buldozer
|
0.78
|
1
|
1
|
1
|
1,06
|
0.74
|
|
O`simlik qatlamini tashish (tashqariga chiqarish)
|
1000 m3
|
1,075
|
2.33
|
УРАЛ-555710
|
2.33
|
1
|
3
|
3
|
1,06
|
0.74
|
|
Kotlovanda ekskavator orqali grunt qazish
|
1000 m3
|
2.825
|
20.74
|
Ekskava-tor
|
20.74
|
2
|
1
|
2
|
1,06
|
9.78
|
|
Gruntni tashish (tashqariga chiqarish)
|
1000 m3
|
2.825
|
62.22
|
УРАЛ-555710
|
62.22
|
2
|
3
|
6
|
1,06
|
9.78
|
|
Transheyada ekskavator orqali grunt qazish
|
1000 m3
|
3.195
|
3.59
|
Ekskava-tor
|
3.59
|
2
|
1
|
2
|
1
|
1.795
|
|
Buldozer yordamida kotlovandagi qoldiq gruntga ishlov berish
|
1000 m3
|
2.825
|
4.93
|
buldozer
|
4.93
|
1
|
1
|
1
|
1,06
|
4.623
|
|
Qo`l yordamida transheyada gruntga ishlov berish
|
100 m2
|
0,441
|
8.28
|
|
-
|
1
|
3
|
3
|
1,3
|
2.12
|
|
|
|
|
102.86
|
|
|
|
|
|
|
29.578
|
|
IV.YER ISHLARINI BAJARISHDAGI TEXNIK-IQTISODIY KO`RSATKICHLAR.
Islarni bajarish grafigi bo`yicha qabul qilinadigan ishlaring umumiy davomiyligi T, kun.
T= 29.578 kun.
Yer ishlarining meyoriy mehnat sarfi Qm, mehnat sarfi kalkulatsiyasi bo`yicha olinadi, kishi-kun.
Qm=102.86 kishi-kun.
Yer ishlarining loyihaviy mehnat sarfi QL, quyidagi formula bilan aniqlanadi.
Bunda Ni- i jarayonni bajarish uchun smenadagi ishchilarning soni, ishlarni bajarish grafigini 8-ustun bo`yicha olinadi; Ti-ijarayonning kunlar bilan ifodalanadigan davomiyligi, ishlarni bajarish grafigining 11 ustuni bo`yicha olinadi; m- sutkadagi smenalarning i-soni, 7 ustundan olinadi.
QL=0.74+3*0.74+2*9.78+6*9.78+2*1.795+1*4623+3*2.12=117.4162
Yer ishlarining unumdorligi quyidagi formula orqali aniqlanadi.
П
П