Of the 29.3GW power generating capacity the country will have in 2030, the Government of
Uzbekistan amongst other things, aims for renewable energy to contribute almost half (8GW)
with wind power accounting for 3GW.
Figure 1-2 Power Generating Capacity Growth Between 2019 and 2030
Source: Uzbekistan 2030 Energy Strategy Concept Note, 2020
1.1
The Project
As part of the Uzbekistan 2030 Energy Strategy, ACWA Power has signed an implementation
agreement with the Ministry of Energy in Uzbekistan for developing, building and operating a
500MW Wind Farm in Dzhankeldy (herein after referred to as ‘the Project’) on two adjacent
plots of land in Peshku District.
ACWA Power have since established a Project Company, ‘FE ACWA Power Dzhankeldy Wind
LLC’ registered in the Republic of Uzbekistan with registration number 839766. ACWA Power
Dzhankeldy Wind LLC has entered into a 25-year Power Purchase Agreement (PPA) with JSC
‘National Electric Grids of Uzbekistan’, which is based on the ultimate operations of the Project.
The Project will include the development
financing, construction, operation and maintenance
Dzhankeldy 500MW Wind Farm
ESIA Volume 2- Main Text, Tables & Figures
3
of the Wind Farm including 79 wind turbine generators (WTGs)
and wind farm electrical
substations.
The Project scope
also includes development, financing, construction
and transfer of the
Purchaser Electrical Facilities
1
(PEF) and common electrical facilities shared with Bash 500MW
Wind Farm, switchyard (with transformers) and 500/220 kV pooling station.
JSC National Electric Networks of Uzbekistan will be responsible
for the operations and
maintenance of the PEF following transfer from ACWA Power and the development, financing,
construction, operation and maintenance of the OHTL upstream from the PEF.