Qurilish mashinalari, qurilish jarayonlari texnologiyasi


III.Mehnat sarfi va mshinani ishlash vaqti sarfining kalkulatsiyasi va ishlab chiqarish grafigini tuzish


Download 285.82 Kb.
bet6/6
Sana06.12.2021
Hajmi285.82 Kb.
#178844
1   2   3   4   5   6
Bog'liq
Курс иши

III.Mehnat sarfi va mshinani ishlash vaqti sarfining kalkulatsiyasi va ishlab chiqarish grafigini tuzish.

Asos

ШНК bo`yicha



Ishlarning nomi

Ishlarning hajmi

Mehnat sarfi

Mashina ishlash vaqtining sarfi.

izoh

O`lchov birligi.

Miqdor

Mahsulot birligi uchun, kishi-soat

Butun hajm uchun, kis-soat

Mahsulot birligi uchun, mash-soat

Butun hajm uchun, mash-soat

1

2

3

4

5

6

7

8

9

4.01.02-04

Jadval


1.01-030-14

Buldozer yordamida o`simlik qatlamini qirqib olish.

1000m3

1.075

5.93

6.37

5.93

6.37




-

O`simlik qatlamini tashish (tashqariga chiqarish)

1000m3

1.075

17.79

19.12

17.79

19.12




4.01.02-04

Jadval


1.01-014-02

Kotlovanda ekskavator orqali grunt qazish

1000m3

2.825

60.20

170.065

60.20

170.065




-

Gruntni tashish (tashqariga chiqarish)

1000m3

2.825

180.60

510.195

180.60

510.195




4.01.02-04

Jadval


1.01-005-10

Transheyada ekskavator orqali grunt qazish

1000m3

3.195

9.20

29.394

9.20

29.394




4.01.02-04

Jadval


1.01-014-03

Bulldozer yordamida kotlovandagi qoldiq gruntga ishlov berish

1000m3

2.825

14.30

40.398

14.30

40.398




4.01.02-04

Jadval


1.02-057-03

Qo`l yordamida transheyada gruntga ishlov berish

100m3

0.441

154,0

67.914

-

-

























775.542





Ishlarni bajarish kalendarniy grafigi.

Ishlarning nomi

Ishlarning hajmi

Ishlarning mehnat srfi Q, kishi -kun

Qabul qilingan mashinalar

Sutkadagi smenalar soni, m

Smenadagi ishchilar soni, n

Sutkadagi brigada tarkibi m*n

Meyor (norma)ni bajarish koeefitsienti K

Ishlarning loyihaviy davomiyligi, T

Ishchi kunlar

O`lchov birligi

Miqdori

Nomlami-shi

Mash.-sm.lar miqdori




1

2

3

4

5

6

7

8

9

10

11

12

Buldozer yordamida o`simlik qatlamini qirqib olish

1000m3

1,075

0.78

Buldozer

0.78

1

1

1

1,06

0.74




O`simlik qatlamini tashish (tashqariga chiqarish)

1000 m3

1,075

2.33

УРАЛ-555710



2.33

1

3

3

1,06

0.74




Kotlovanda ekskavator orqali grunt qazish

1000 m3

2.825

20.74

Ekskava-tor

20.74

2

1

2

1,06

9.78




Gruntni tashish (tashqariga chiqarish)

1000 m3

2.825

62.22

УРАЛ-555710

62.22

2

3

6

1,06

9.78




Transheyada ekskavator orqali grunt qazish

1000 m3

3.195

3.59

Ekskava-tor



3.59

2

1

2

1

1.795




Buldozer yordamida kotlovandagi qoldiq gruntga ishlov berish

1000 m3

2.825

4.93

buldozer

4.93

1

1

1

1,06

4.623




Qo`l yordamida transheyada gruntga ishlov berish

100 m2

0,441

8.28




-

1

3

3

1,3

2.12













102.86



















29.578






IV.YER ISHLARINI BAJARISHDAGI TEXNIK-IQTISODIY KO`RSATKICHLAR.

  1. Islarni bajarish grafigi bo`yicha qabul qilinadigan ishlaring umumiy davomiyligi T, kun.

T= 29.578 kun.

  1. Yer ishlarining meyoriy mehnat sarfi Qm, mehnat sarfi kalkulatsiyasi bo`yicha olinadi, kishi-kun.

Qm=102.86 kishi-kun.

  1. Yer ishlarining loyihaviy mehnat sarfi QL, quyidagi formula bilan aniqlanadi.

Bunda Ni- i jarayonni bajarish uchun smenadagi ishchilarning soni, ishlarni bajarish grafigini 8-ustun bo`yicha olinadi; Ti-ijarayonning kunlar bilan ifodalanadigan davomiyligi, ishlarni bajarish grafigining 11 ustuni bo`yicha olinadi; m- sutkadagi smenalarning i-soni, 7 ustundan olinadi.



QL=0.74+3*0.74+2*9.78+6*9.78+2*1.795+1*4623+3*2.12=117.4162

  1. Yer ishlarining unumdorligi quyidagi formula orqali aniqlanadi.