Dzhankeldy Wind Power Project


Download 6.64 Mb.
Pdf ko'rish
bet66/203
Sana13.09.2023
Hajmi6.64 Mb.
#1676820
1   ...   62   63   64   65   66   67   68   69   ...   203
Bog'liq
56086-001-esia-en

ESCRIPTION
 
Name of the OHTL 
33/500kV Bash WPP to existing 500kV 
Karakul substation 
Length
162.260km 
No of points of intersections 
18 
Number of transmission line crossings

Number of intersections of the design 
transmission line 

Number of railway line crossings 

Number of pipeline crossings 

Number of highway crossings 

Number of small road crossings 

Number of canal/irrigation ditch crossings 
13 
Source: Pre-feasibility Study for 500kV Transmission Lines (draft), 2021 
Environmental & Social Aspects 
According to the pre-feasibility study, the 162km OHTL is found within a 50km of IBAs as shown 
in the figure below. The closest IBA site is lake Ayakagitma at approximately 6.7km to the north 
west of the OHTL. Additional ecological studies (i.e., herpetological, invertebrates, botanical 
and ornithological surveys) along the OHTL have been undertaken under the Bash 500MW 
Wind Farm ESIA (subject of a separate ESIA). 
 


Dzhankeldy 500MW Wind Farm 
ESIA Volume 2- Main Text, Tables & Figures 
97 
Figure 2-46 IBAs found within 1km, 10km & 50km of the OHTL 
Source: Pre-feasibility Study for 500kV Transmission Lines (draft), 2021 
The proposed Line 1 (green) crosses through four agricultural lands owned by local farmers 
and on the eastern border of land belonging to Qirobod Mavjlari LLC and Kumush Kalava LLC 
but this land will not be impacted. Line 2 (violet) crosses through five agricultural lands and 
would not have any impact on other social infrastructure located near or around the Karakul 
sub-station (ACWA Power, 2021). Impacts on the Project Affected Persons (PAPs) are assessed 
on the Project-specific Resettlement Action Framework (RAF) and Resettlement Action Plan 
(RAP). 
Based on the above factors and in order to avoid residential areas, community 
structures/facilities and agricultural areas as far as practicable, the pre-feasibility study 
recommends that Line 1 is the best alignment between Bash to Karakul due to the limited 
number of crossings.
In August 2021, this OHTL Line 1 was slightly revised to avoid small farmlands along the route as 
far as practicable and to ensure the line connects to the available spare bay at Karakul 
substation. 
The proposed Dzhanekldy 
– Bash – Kurakul OHTL alignment was submitted to NEGU by ACWA 
Power and is as shown in the figure below. 
 


Dzhankeldy 500MW Wind Farm 
ESIA Volume 2- Main Text, Tables & Figures 
98 

Download 6.64 Mb.

Do'stlaringiz bilan baham:
1   ...   62   63   64   65   66   67   68   69   ...   203




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling