Pitfalls in Time Schedule Planning 95
In
some cases, activity A may begin and, after a certain time period,
activity B begins. This period is called the “lag time.”
A computer
can perform this task easily, but, in general, there are two
main methods: the arrow diagram
and the precedence diagram, as shown
in Figure 3.4.
3.5.1 Gantt
Chart
In general, the relations between activities are usually in series or parallel.
The relation depends on the nature of the activities and this should be con-
sidered in preparing the time schedule.
The Gantt chart is the oldest and most traditional
method used to present
project schedules to this day. But, the relations between all the activities are
not presented well by this method and you cannot go through the detailed
activity as accurately. Therefore, it would only be useful
in presentations
for high-level management, as it presents enough information for level one
of
the schedule, but for more detail another method is needed.