Project Management in the Oil and Gas Industry
Download 1.92 Mb. Pdf ko'rish
|
2.Project management in the oil and gas industry 2016
Precedence diagram
Start A B C Finish D E F No. ES EF D LS LF Activity D: Duration ES: Early Start EF: Early Finish LS: Latest Start LF: Latest Finish Figure 3.6 Method of preceding diagram. 98 Project Management in the Oil and Gas Industry analysis is used in a number of areas of the computer industry, construction industries, and in planning the shutdown for maintenance in refineries. This analysis has confirmed its applicability and importance by its appli- cation in different projects. Contracting companies can use it successfully because of its role in solving problems of coordination between various activities in a project that have considerable degrees of complexity and its role in planning the time required for implementing each activity. This method has made it possible to complete a project within the time planned and the overall schedule. PERT was developed primarily to simplify the planning and scheduling of large and complex projects. It was able to incorporate uncertainty by making it possible to schedule a project while not knowing precisely the details and durations of all the activities. Hence, the PERT method depends on using statistics and probability theory, so it is now the main key for the project risk assessment from the time schedule point of view. In some cases, it is required to compress the time schedule and items by a crashing technique as to reduce the time and calculate its impact out the cost and let them work overtime. The other way is by using a fast tracking method. This is done by letting some activities be in parallel which are usually in series. As we discussed, in the oil and gas industry, time is very critical. For example, we can start to construct the foundation for a petro- leum processing plant before finishing 25 percent of the engineering deliv- erables. Fast tracking often results in rework and usually increases risk. Any dependencies between activities require specification of a lead or lag to accurately define the relationship. An example of lead in a start- to-finish dependency with a ten day lead is in a case where the successor activity starts ten days before the predecessor has completed. An example of a lag is when there might be a desire to schedule a two week delay (lag) between ordering the equipment and using or installing it. Download 1.92 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling