Dzhankeldy Wind Power Project
Table 2-10 Key Project Milestone/Timeline Dates
Download 6.64 Mb. Pdf ko'rish
|
56086-001-esia-en
Table 2-10 Key Project Milestone/Timeline Dates
M ILESTONES D ATE Signing Project Agreements (PPA; Investment Agreement) 24 th January 2021 Presidential Decrees 22 nd February 2021 Land Allotment Orders 19 & 23 March 2021 Limited Notice to Proceed (LNTP) 1 st March 2022 Full Notice to Proceed (FNTP) 1 st May 2022 Completion of 1 st WTG Foundation 25 th September 2022 Completion of all WTG Foundations 13 th September 2023 Completion of Substation Civil Work 27 th August 2023 Completion of Substation and MV Network Connection 31 st October 2023 Mechanical Completion 2 nd December 2023 Connection Date 18 th December 2023 Initial Energization Date 19 th December 2023 Scheduled Commercial Operation Date 29 th February 2024 2.7 Decommissioning of the Project Potential impacts relating to decommissioning will be similar to those encountered during the construction phase. Due to the small footprint of the project WTG, all structures and infrastructure could feasibly be demobilised with only few elements having the potential to cause long-term legacy impacts or other widespread pollution incidents. Given that the decommissioning phase is not expected for at least 25 years from the Commercial Operation Date, there are no specific requirements provided for the decommissioning of the project. As such, it is not considered practical or of value to speculate on future environmental and social conditions including the sensitivity of current or future receptors at this time, or facilities that may or may not be present to handle wastes etc., or the extent of environmental and social regulation that may exist. Hence, it is proposed that all impacts relating to decommissioning stage will be planned to be approached and mitigated via a specific decommissioning plan and updated baseline surveys prepared closer to the time of decommissioning as it would be able to account for changes in regulation, improvements in technology and requirements for re-use and recycling of components and materials and methods of demobilisation. The decommissioning plan would be developed prior to decommissioning and would be based on the project’s ESMS. Download 6.64 Mb. Do'stlaringiz bilan baham: |
Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling
ma'muriyatiga murojaat qiling