Dzhankeldy Wind Power Project


Table 2-10 Key Project Milestone/Timeline Dates


Download 6.64 Mb.
Pdf ko'rish
bet56/203
Sana13.09.2023
Hajmi6.64 Mb.
#1676820
1   ...   52   53   54   55   56   57   58   59   ...   203
Bog'liq
56086-001-esia-en

Table 2-10 Key Project Milestone/Timeline Dates 
M
ILESTONES
 
D
ATE
 
Signing Project Agreements (PPA; Investment 
Agreement) 
24
th
January 2021 
Presidential Decrees 
22
nd
February 2021 
Land Allotment Orders 
19 & 23 March 2021 
Limited Notice to Proceed (LNTP) 
1
st
March 2022 
Full Notice to Proceed (FNTP) 
1
st
May 2022 
Completion of 1
st
WTG Foundation 
25
th
September 2022 
Completion of all WTG Foundations 
13
th
September 2023 
Completion of Substation Civil Work 
27
th
August 2023 
Completion of Substation and MV Network Connection 
31
st
October 2023 
Mechanical Completion 
2
nd
December 2023 
Connection Date 
18
th
December 2023 
Initial Energization Date 
19
th
December 2023 
Scheduled Commercial Operation Date 
29
th
February 2024 
2.7
Decommissioning of the Project
Potential impacts relating to decommissioning will be similar to those encountered during the 
construction phase. Due to the small footprint of the project WTG, all structures and 
infrastructure could feasibly be demobilised with only few elements having the potential to 
cause long-term legacy impacts or other widespread pollution incidents. 
Given that the decommissioning phase is not expected for at least 25 years from the 
Commercial Operation Date, there are no specific requirements provided for the 
decommissioning of the project. As such, it is not considered practical or of value to speculate 
on future environmental and social conditions including the sensitivity of current or future 
receptors at this time, or facilities that may or may not be present to handle wastes etc., or the 
extent of environmental and social regulation that may exist. 
Hence, it is proposed that all impacts relating to decommissioning stage will be planned to be 
approached and mitigated via a specific decommissioning plan and updated baseline 
surveys prepared closer to the time of decommissioning as it would be able to account for 
changes in regulation, improvements in technology and requirements for re-use and recycling 
of components and materials and methods of demobilisation. The decommissioning plan 
would be developed prior to decommissioning and would be based on the project’s ESMS.

Download 6.64 Mb.

Do'stlaringiz bilan baham:
1   ...   52   53   54   55   56   57   58   59   ...   203




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling