Dzhankeldy 500MW Wind Farm
ESIA Volume 2- Main Text, Tables & Figures
92
route considered for the Dzhankeldy to Bash OHTL due to the
environmental and social
constraints identified along the proposed alignment.
The figure below shows the new alignment options considered in August 2021.
Figure 2-44 The Three (3) OHTL Alignment Options - August 2021
Note:
Green Line: OHTL 500kV Line 1
Violet Line: OHTL 500kV Line 2
Dark Blue Line: OHTL 500kV Line 3
Dzhankeldy 500MW Wind Farm
ESIA Volume 2- Main Text, Tables & Figures
93
2.8.6.1
Dzhankeldy to Bash OHTL
The 500kV will start from 33/500kV Dzhankeldy substation to the Bash Wind Farm 33/500kV
substation. In some sections, the proposed OHTL runs parallel to existing OHTL near the Bash
site while the rest of the alignment is parallel to an access road and highway.
Additionally,
there are a few hills with an elevation of 20-30m along the alignment.