Dzhankeldy 500MW Wind Farm
ESIA Volume 2- Main Text, Tables & Figures
76
2.4.5
Worker Accommodation
It is understood that the location of worker accommodation for the Wind Farm and OHTL will
be within the Project site and located in the same area as the proposed laydown area (please
see proposed location in the figure below). Such worker accommodation
is expected to
house Project Company and EPC Contractor staff. At this stage,
the exact location of the
worker accommodation and other workers accommodation requirements for e subcontractor
have not been confirmed. However, it is expected that the necessary facilities and standards
of facilities for all worker accommodation/camp will be specified
by the Project Company
and will be in accordance with the IFC/EBRD Worker Accommodation Processes and
Standards and recent COVID-19 requirements including:
Interim Advice for IFC Client on Supporting Workers in the Context of COVID-19
(April 2020)
Interim Advice for IFC and EBRD Clients on Migrant Workers and COVID-19 (July
2020)
ADB Interim Advisory Note: Protecting the Safety and
Well Being of Workers and
Communities from COVID-19 (2020).
Figure 2-29 Indicative Location of Laydown Areas and Worker Accommodation for
Project Company and EPC Contractor Staff (ref. Red Square)
Dzhankeldy 500MW Wind Farm
ESIA Volume 2- Main Text, Tables & Figures
77
2.4.6
Vehicles, Equipment and Heavy Machinery Requirements
EPC Contractors/sub-contractors responsible for different construction activities
within the site
will make use of various kinds of vehicles, equipment and
heavy machinery during the
construction phase of the wind farm. The anticipated vehicles, equipment and machinery to
be used on site during the site preparation and construction activities include but not limited
to: