21
some of the other requirements. We can make our recommendations
to the relevant state
organisations.
Committee for the Development of Sericulture and Wool Industry: Are the sizes of the allocated
land for both Projects clearly indicated in the Presidential Decrees No. 5001 and No. 5003?
ACWA Power: No, the Presidential Decree does not include these details. However, the
coordinates of the Project are indicated in the agreements with NEGU and Ministry of Foreign
Trade and Investments.
Committee for the Development of Sericulture and Wool Industry:
Will the turbine placement
prevent herders from grazing?
ACWA Power: The turbines will not prevent herders from grazing after the construction works.
Committee for the Development of Sericulture and Wool Industry: My
question is to Bukhara
Association, do you have any concerns about the Project?