Resource Hiring 161
Figures 5.8 and 5.9 represent the distribution of the resources in two
cases and the harmony of resources distribution
is visible if we use the
latest start activity as discussed before.
It is worth mentioning here that, in the case of large projects,
a meeting
must be held between a representative of the owner, the consultant, and
the contractor.
In
this meeting, the contractor should define the personnel and equip-
ment that will be found at the site in accordance with the scheduled plan.
In this meeting, all the representative engineers should agree on the
resources.
Noting that, each party will distribute resources according to its own
benefits. As an example, the contractor in the
negotiation will have had
more than one reason for the distribution of resources, advertising and
most other causes are undeclared as he
may need some personnel for
another project at a particular time or need to transport heavy equipment,
such as cranes, to another site or other important resources. At the same
time, he wants to delay some of the items to be
cost assembled in another
project and this will be studied in the chapter on costs.
From the owner point of view, it is important to complete all the items
as soon as possible. The owner often does
not want to consume all the