2.4.2.1
Wind Farm 
Temporary construction laydown area(s) will be established towards the north eastern extent 
of the Project site. These areas will be required during the construction phase of the Project for 
the Wind Farm & the Dzhankeldy to Bash OHTL and for the storage of materials by the 
Engineering Procurement and Construction (EPC) contractor as well as sub-contractors. After 
completion of construction, the construction laydown areas will be disassembled, and the 
area will be returned to its original condition. The laydown area will include: 
 
Office containers; 
 
Storage areas for equipment
 
Parking areas; 
 
Bathroom and waste collection facilities; 
 
Equipment for power generation; 
 
Communications equipment; and 
 
Other miscellaneous small items as required. 
2.4.2.2
OHTL 
Where temporary construction laydown area(s) will be established along the OHTL 
corridor/ROW, these areas will be required for the storage of materials such as pre-assembled 
tower sub-structures, for the further assembly of these sub-structures into final tower structures, 
for storage of foundation reinforcement steel or steel tower metal bars, tools & equipment to 
be used by the Engineering Procurement and Construction (EPC) contractor as well as sub-
contractors responsible for OHTL construction. 
It is understood that the indicative length of the laydown areas will be approximately 3-5km of 
the construction transmission line route covering on average 11 to 12 towers. Each laydown 
areas is anticipated to be approximately 100m X 50m in area. Following assembly of the tower, 
the assembled towers will be transported from the laydown area to each tower construction 
site. Each laydown areas is anticipated to be approximately 100m X 50m in area and will be 
in use for a few weeks only. After completion of construction, the construction laydown areas 
will be disassembled, and the area will be returned to its original condition.


Dzhankeldy 500MW Wind Farm 
ESIA Volume 2- Main Text, Tables & Figures 
74 
2.4.3 
Utility Requirements 
The Engineering, Procurement and Construction (EPC) contractor will be solely responsible for 
all construction utilities required for the Wind Farm and OHTL including power supply, potable 
water, firefighting supplies and systems, erosion and sedimentation control, waste 
management and temporary medical and welfare facilities. Where possible, the EPC 
contractor will connect to existing utilities, where this is not possible utilities will be provided by 
water tankers and generators.

Download 6.64 Mb.

Do'stlaringiz bilan baham:
1   ...   47   48   49   50   51   52   53   54   ...   203




Ma'lumotlar bazasi mualliflik huquqi bilan himoyalangan ©fayllar.org 2024
ma'muriyatiga murojaat qiling